11142-11144 N BLUCHER AVE 91344

Certificate Information: 11142-11144 N BLUCHER AVE 91344

Application / Permit
23016-20000-00840
Plan Check / Job No.
B23VN00366
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT 23'-11" x 19'-3" (E) ATTACHED GARAGE AND 12'-2" x 13'-2" PORTION OF (E) SFD TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A). ALL PER WFPP.
Permit Issued
Issued on 3/31/2023
Issuing Office
Current Status
CofO Issued on 4/11/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/12/2023 APPLICANT
Assigned to Plan Check Engineer 1/13/2023 SERGIO MUNIZ
Corrections Issued 1/14/2023 SERGIO MUNIZ
Building Plans Picked Up 1/17/2023 APPLICANT
Plan Check Approved 3/30/2023 SARKIS HARABEDIAN
Issued 3/31/2023 APPLICANT
CofO in Progress 3/29/2024 JENNIFER RABUCHIN
CofO Issued 4/11/2024 RUBEN SALAS
Permit Finaled 4/11/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/19/2023 COLIN LOREDO
Sewer availability Cleared 1/19/2023 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 3/28/2023 COLIN LOREDO
Grading Pre-Inspection Cleared 3/28/2023 MICHAEL TEMPLE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/18/2023 Approved JENNIFER RABUCHIN
Deputy Drilled-In Anchors 5/22/2023 Conditional Approval MICHAEL SMITH
Footing/Foundation/Slab 5/24/2023 Approved JENNIFER RABUCHIN
PLUMBING-Rough 5/24/2023 Partial Approval JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/14/2023 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 6/14/2023 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Rough 6/14/2023 Not Ready for Inspection JENNIFER RABUCHIN
MERV13>=Rough 6/14/2023 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/27/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 6/27/2023 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 6/27/2023 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 7/10/2023 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 7/10/2023 Approved JENNIFER RABUCHIN
Green Building Rough 7/10/2023 Approved JENNIFER RABUCHIN
HVAC-Rough 7/10/2023 Approved JENNIFER RABUCHIN
MERV13>=Rough 7/10/2023 Approved JENNIFER RABUCHIN
PLUMBING-Rough 7/10/2023 Approved JENNIFER RABUCHIN
Insulation 8/4/2023 Approved JENNIFER RABUCHIN
Drywall Nailing 8/21/2023 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 8/21/2023 Partial Approval JENNIFER RABUCHIN
Shower Pan 8/21/2023 Corrections Issued JENNIFER RABUCHIN
Sewer 9/22/2023 Approved JENNIFER RABUCHIN
Shower Pan 9/22/2023 Approved JENNIFER RABUCHIN
Final 3/20/2024 Corrections Issued JENNIFER RABUCHIN
Green Building Final 3/20/2024 Approved JENNIFER RABUCHIN
MERV13>=Final 3/20/2024 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 3/20/2024 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 3/20/2024 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 3/28/2024 Approved JENNIFER RABUCHIN
Final 3/28/2024 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 3/28/2024 Approved JENNIFER RABUCHIN
MERV13>=Final 3/28/2024 Approved JENNIFER RABUCHIN
PLUMBING-Final 3/28/2024 Approved JENNIFER RABUCHIN