9223 N SWINTON AVE 91343
Certificate Information: 9223 N SWINTON AVE 91343
- Application / Permit
- 23016-20000-00821
- Plan Check / Job No.
- B23VN00354
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EX DETACHED 18'X22'6" GARAGE INTO ACCESSORY DWELLING UNIT PER LAMC 12.22A.33(c) & (d) WITH IRR SHAPED 31'X22'ADDITION. ALL WORK PER WFPP. "COMPLY WITH DEPARTMENT ORDER effective date 10/06/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE" **SEE COMMENTS**
- Permit Issued
- Issued on 10/12/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2023 | SERGIO MUNIZ |
| Corrections Issued | 1/14/2023 | SERGIO MUNIZ |
| Building Plans Picked Up | 1/24/2023 | APPLICANT |
| Applicant returned to address corrections | 4/27/2023 | JESSE ARELLANO |
| Applicant returned to address corrections | 6/28/2023 | ISIS ARGUETA |
| Applicant returned to address corrections | 7/19/2023 | GIOVANNY CHAVEZ |
| Plan Check Approved | 10/12/2023 | ISIS ARGUETA |
| Issued | 10/12/2023 | APPLICANT |
| CofO in Progress | 7/23/2024 | MARK DOVICO |
| Permit Finaled | 8/7/2024 | DAVID JAMES |
| CofO Issued | 8/7/2024 | DAVID JAMES |
| Permit Finaled | 8/7/2024 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 4/10/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 4/11/2023 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 10/7/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 10/7/2023 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 10/12/2023 | SERGIO MUNIZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIO CUEVAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/28/2023 | Approved | MARK DOVICO |
| Underground Mechanical | 11/28/2023 | Approved | MARK DOVICO |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2023 | Approved | MARK DOVICO |
| BUILDING-Rough-Frame | 12/15/2023 | Corrections Issued | MARK DOVICO |
| ELECTRICAL-Rough | 12/15/2023 | Approved | MARK DOVICO |
| Green Building Rough | 12/15/2023 | Corrections Issued | MARK DOVICO |
| HVAC-Rough | 12/15/2023 | Approved | MARK DOVICO |
| Interior/Exterior Lathing | 12/15/2023 | Partial Approval | MARK DOVICO |
| PLUMBING-Rough | 12/15/2023 | Approved | MARK DOVICO |
| Insulation | 12/20/2023 | Approved | MARK DOVICO |
| Sewer | 12/20/2023 | Approved | MARK DOVICO |
| Drywall Nailing | 1/3/2024 | Approved | MARK DOVICO |
| Green Building Rough | 1/3/2024 | Approved | MARK DOVICO |
| Interior/Exterior Lathing | 1/3/2024 | Approved | MARK DOVICO |
| BUILDING-Rough-Frame | 4/5/2024 | Conditional Approval | MARK DOVICO |
| Final | 4/5/2024 | Corrections Issued | MARK DOVICO |
| Green Building Final | 4/5/2024 | Conditional Approval | MARK DOVICO |
| SGSOV-Seismic Gas S/O Valve | 4/5/2024 | SGSOV Not Ready | MARK DOVICO |
| Smoke Detectors | 4/5/2024 | Conditional Approval | MARK DOVICO |
| BUILDING-Rough-Frame | 6/18/2024 | Corrections Issued | MARK DOVICO |
| Final | 6/18/2024 | Corrections Issued | MARK DOVICO |
| Green Building Final | 6/18/2024 | Corrections Issued | MARK DOVICO |
| Smoke Detectors | 6/18/2024 | Approved | MARK DOVICO |
| BUILDING-Rough-Frame | 7/23/2024 | Approved | MARK DOVICO |
| Final | 7/23/2024 | OK to Issue CofO | MARK DOVICO |
| Green Building Final | 7/23/2024 | Approved | MARK DOVICO |