10064 W RIVERSIDE DR 91602
Certificate Information: 10064 W RIVERSIDE DR 91602
- Application / Permit
- 23016-20000-00596
- Plan Check / Job No.
- B22VN19283
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Bank
- Work Description
- Tenant improvement to include demo of non-structural partitions and ceiling, construction of new partitions, ceiling, power, finishes, new ADA restrooms, new HVAC units.
- Permit Issued
- Issued on 5/8/2023
- Issuing Office
- Current Status
- Permit Finaled on 11/28/2023
Permit Application Status History
| Submitted | 1/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2023 | FERNANDO FLORES |
| Corrections Issued | 1/16/2023 | FERNANDO FLORES |
| Plan Check Approved | 2/4/2023 | FERNANDO FLORES |
| Issued | 5/8/2023 | APPLICANT |
| Permit Finaled | 11/28/2023 | ROBERT DAVIS |
Permit Application Clearance Information
| "Q" conditions | Cleared | 1/24/2023 | KENTON TRINH |
| ZI | Cleared | 1/24/2023 | KENTON TRINH |
| Supp. Use District POD/CDO/TDO | Cleared | 1/25/2023 | ADRINEH MELKONIAN |
Contact Information
| Architect | Kamus,, John Howard; Lic. No.: C20397 | 1965 YOSEMITE AVE SUITE #205 SIMI VALLEY, CA 93063 |
| Architect | Kamus,, John Howard; Lic. No.: NA20397 | , |
| Contractor | Wilson Delang Construction Group; Lic. No.: 989586-B | , |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 6/9/2023 | Conditional Approval | ROBERT DAVIS |
| Insulation | 6/15/2023 | Partial Approval | ROBERT DAVIS |
| Deputy Drilled-In Anchors | 6/16/2023 | Conditional Approval | ROBERT DAVIS |
| Pre-Inspection | 6/20/2023 | Conditional Approval | CAMERON CHABAN |
| Light Gage Steel Frame | 6/22/2023 | Not Ready for Inspection | ROBERT DAVIS |
| Drywall Nailing | 6/28/2023 | Partial Approval | ROBERT DAVIS |
| Deputy Drilled-In Anchors | 7/7/2023 | Conditional Approval | ROBERT DAVIS |
| Footing/Foundation/Slab | 7/10/2023 | Approved | ROBERT DAVIS |
| Deputy Drilled-In Anchors | 7/14/2023 | Conditional Approval | JEFFREY DURAN |
| Drywall Nailing | 7/17/2023 | Not Ready for Inspection | ROBERT DAVIS |
| Partition/T-Bar Ceiling | 7/17/2023 | Not Ready for Inspection | ROBERT DAVIS |
| Wood Frame | 7/18/2023 | Partial Approval | ROBERT DAVIS |
| Interior/Exterior Lathing | 7/20/2023 | Partial Approval | ROBERT DAVIS |
| Partition/T-Bar Ceiling | 7/27/2023 | Not Ready for Inspection | ROBERT DAVIS |
| Deputy Drilled-In Anchors | 7/28/2023 | Conditional Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 7/28/2023 | Conditional Approval | ROBERT DAVIS |
| Deputy Drilled-In Anchors | 7/31/2023 | Conditional Approval | ROBERT DAVIS |
| Deputy Steel/Welding | 7/31/2023 | Conditional Approval | ROBERT DAVIS |
| Partition/T-Bar Ceiling | 8/2/2023 | Approved | ANDREW DORSO |
| Drywall Nailing | 8/9/2023 | Not Ready for Inspection | KENNETH ROBERTS |
| Drywall Nailing | 8/14/2023 | Approved | ANDREW DORSO |
| T-Bar Ceiling | 8/14/2023 | Partial Inspection | ANDREW DORSO |
| Partition/T-Bar Ceiling | 9/1/2023 | Approved | ROBERT DAVIS |
| Partition/T-Bar Ceiling | 9/7/2023 | Approved | STEVEN LEVITT |
| Final | 10/4/2023 | Corrections Issued | ROBERT DAVIS |
| Green Building Final | 10/4/2023 | Approved | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 10/4/2023 | SGSOV Approved | ROBERT DAVIS |
| Smoke Detectors | 10/4/2023 | Not Ready for Inspection | ROBERT DAVIS |
| Final | 10/23/2023 | Not Ready for Inspection | KENNETH ROBERTS |
| Smoke Detectors | 10/23/2023 | Not Ready for Inspection | KENNETH ROBERTS |
| Final | 11/28/2023 | Permit Finaled | ROBERT DAVIS |
| Smoke Detectors | 11/28/2023 | Approved | ROBERT DAVIS |