11046 W DEBBY ST 91606
Certificate Information: 11046 W DEBBY ST 91606
- Application / Permit
- 23016-20000-00458
- Plan Check / Job No.
- B22VN19273
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Recreation Room
- Work Description
- EPLAN: CONVERT (E) ATTACHED GARAGE INTO A (N) ATTACHED 18'-6" x 18'-6" RECREATION ROOM. ALL WORK PER ENGINEERING. SEE COMMENTS ***LOT IS ELIGIBLE FOR AB 2097 AND DOES NOT NEED REPLACEMENT PARKING ON THE LOT.
- Permit Issued
- Issued on 11/1/2023
- Issuing Office
- Current Status
- CofO Issued on 7/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/10/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2023 | GURUNATH NESARAJAH |
| Corrections Issued | 1/12/2023 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 2/2/2023 | ALFRED RAMIREZ |
| Applicant returned to address corrections | 2/11/2023 | ROSENDO MEDINA |
| Applicant returned to address corrections | 2/27/2023 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 5/5/2023 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 7/17/2023 | JOSEPH RAFOLS |
| Plan Check Approved | 8/3/2023 | JOSEPH RAFOLS |
| Issued | 11/1/2023 | APPLICANT |
| CofO in Progress | 6/30/2025 | ROBERTO PALACIOS-LOPEZ |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
| CofO Issued | 7/8/2025 | RUBEN SALAS |
| Permit Finaled | 7/8/2025 | RUBEN SALAS |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Corgrove Construction Industries Inc; Lic. No.: 1094489-B | , |
| Engineer | Truong,, Phong; Lic. No.: C70784 | 20439 E CRESTLINE DRIVE WALNUT, CA 91789 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 11/7/2023 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 11/7/2023 | Not Ready for Inspection | JOHN HAYES |
| Sewer | 11/7/2023 | Not Ready for Inspection | JOHN HAYES |
| Wood Frame | 11/7/2023 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 12/11/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 12/11/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| Wood Frame | 12/11/2023 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 2/29/2024 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 2/29/2024 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Rough | 2/29/2024 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 2/29/2024 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Rough | 3/5/2024 | Partial Approval | JOHN HAYES |
| ELECTRICAL-Rough | 3/29/2024 | Corrections Issued | THOMAS FINNILA |
| ELECTRICAL-Rough | 6/3/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Insulation | 6/3/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Wood Frame | 6/3/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 6/13/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 6/13/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Wood Frame | 6/13/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Pre-Inspection | 6/20/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Special/Order Compliance | 6/20/2024 | Partial Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 8/7/2024 | Partial Approval | ROBERTO PALACIOS-LOPEZ |
| ELECTRICAL-Rough | 8/7/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 8/7/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| HVAC-Rough | 8/7/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 8/7/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Pre-Inspection | 8/7/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| BUILDING-Rough-Frame | 8/22/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Insulation | 8/22/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Drywall Nailing | 10/29/2024 | Approved | LOUIS ESCOTO |
| Insulation | 10/29/2024 | Approved | LOUIS ESCOTO |
| Interior/Exterior Lathing | 12/24/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 2/13/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/13/2025 | SGSOV Not Required | ROBERTO PALACIOS-LOPEZ |
| Smoke Detectors | 2/13/2025 | Approved | ROBERTO PALACIOS-LOPEZ |
| Final | 2/19/2025 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Final | 2/21/2025 | OK to Issue CofO | ROBERTO PALACIOS-LOPEZ |