5514 N BONNER AVE 1-35 91601
Certificate Information: 5514 N BONNER AVE 1-35 91601
- Application / Permit
- 23016-20000-00384
- Plan Check / Job No.
- B23VN00101
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- eplan: CONVERT EXISTING RECREATION ROOM INTO AN ACCESSORY DWELING UNIT PER STATE LAW GCS 65852.2(e)(1)(C).
- Permit Issued
- Issued on 6/12/2023
- Issuing Office
- Current Status
- CofO Issued on 7/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/10/2023 | MICHAEL LOPEZ |
| Corrections Issued | 2/21/2023 | MICHAEL LOPEZ |
| Quality Review Completed | 3/2/2023 | TEODORO DIAZ RODRIGUEZ |
| Plan Check Approved | 6/12/2023 | MICHAEL LOPEZ |
| Issued | 6/12/2023 | APPLICANT |
| CofO in Progress | 6/26/2025 | ROBERT DAVIS |
| CofO in Progress | 7/11/2025 | ROBERT DAVIS |
| Permit Finaled | 7/11/2025 | JEFFREY DURAN |
| CofO Issued | 7/11/2025 | JEFFREY DURAN |
| Permit Finaled | 7/11/2025 | JEFFREY DURAN |
Permit Application Clearance Information
| Frnt yard landscape/Water mgmt | Cleared | 3/7/2023 | BRENNEN OBETO |
| Address approval | Cleared | 3/8/2023 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2023 | CARLOS AGUILERA |
| Highway dedication | Cleared | 3/8/2023 | CARLOS AGUILERA |
| Sewer availability | Cleared | 3/8/2023 | CARLOS AGUILERA |
| Fire Marshal Fire Life Safety | Cleared | 5/3/2023 | DOMINIQUE MEDINA |
| DAS Clearance | Cleared | 5/16/2023 | Sarkis Harabedian |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mobed,, Ashkan; Lic. No.: C92493 | 23450 KITTREDGE ST WEST HILLS, CA 91307 |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Insulation | 10/23/2024 | Approved | STEVEN LEVITT |
| Drywall Nailing | 11/13/2024 | Approved | KENNETH ROBERTS |
| Final | 5/23/2025 | Not Ready for Inspection | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 5/23/2025 | SGSOV Approved | ROBERT DAVIS |
| Smoke Detectors | 5/23/2025 | Approved | ROBERT DAVIS |
| Wood Frame | 5/23/2025 | Approved | ROBERT DAVIS |
| Final | 6/4/2025 | Not Ready for Inspection | ROBERT DAVIS |
| Final | 6/26/2025 | OK to Issue CofO | ROBERT DAVIS |