6211 N KRAFT AVE 91606
Certificate Information: 6211 N KRAFT AVE 91606
- Application / Permit
- 23016-20000-00330
- Plan Check / Job No.
- B23VN00086
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER CA GOV. STATE CODE 65852.2(e)(1)(A). WORK PER ENGINEER.
- Permit Issued
- Issued on 5/21/2023
- Issuing Office
- Current Status
- CofO Issued on 1/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/12/2023 | ROSENDO MEDINA |
| Corrections Issued | 1/13/2023 | ROSENDO MEDINA |
| Plan Check Approved | 2/16/2023 | ROSENDO MEDINA |
| Issued | 5/21/2023 | APPLICANT |
| CofO in Progress | 1/3/2024 | JOHN HAYES |
| Permit Finaled | 1/25/2024 | RUBEN SALAS |
| CofO Issued | 1/25/2024 | RUBEN SALAS |
| Permit Finaled | 1/25/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/18/2023 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/18/2023 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/18/2023 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 1/18/2023 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 11 CEDARWOOD DR POMONA, CA 91766 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/6/2023 | Partial Approval | JOHN HAYES |
| Pre-Inspection | 6/6/2023 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 6/29/2023 | Partial Approval | JOHN HAYES |
| PLUMBING-Rough | 6/29/2023 | Approved | JOHN HAYES |
| Deputy Drilled-In Anchors | 7/5/2023 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 7/6/2023 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 7/24/2023 | Corrections Issued | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2023 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 7/24/2023 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 7/27/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 7/27/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/2/2023 | Partial Approval | ROBERT GOLD |
| PLUMBING-Rough | 8/2/2023 | Approved | ROBERT GOLD |
| Shower Pan | 8/2/2023 | Approved | ROBERT GOLD |
| ELECTRICAL-Rough | 8/10/2023 | Corrections Issued | JOHN HAYES |
| ELECTRICAL-Rough | 8/17/2023 | Partial Approval | JOHN HAYES |
| Gas Test | 8/23/2023 | Approved | JOHN HAYES |
| Sewer | 8/23/2023 | Partial Approval | JOHN HAYES |
| Special/Order Compliance | 8/23/2023 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 8/23/2023 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 8/25/2023 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/29/2023 | Approved | JOHN HAYES |
| Green Building Rough | 8/29/2023 | Approved | JOHN HAYES |
| HVAC-Rough | 8/29/2023 | Approved | JOHN HAYES |
| Insulation | 9/8/2023 | Corrections Issued | JOHN HAYES |
| Interior/Exterior Lathing | 9/8/2023 | Not Ready for Inspection | JOHN HAYES |
| Insulation | 9/14/2023 | Approved | JOHN HAYES |
| Drywall Nailing | 9/26/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 9/26/2023 | Approved | JOHN HAYES |
| Final | 11/20/2023 | No Access for Inspection | MICHEL ABAJAN |
| Green Building Final | 11/20/2023 | No Access for Inspection | MICHEL ABAJAN |
| HVAC-Final | 11/20/2023 | No Access for Inspection | MICHEL ABAJAN |
| PLUMBING-Final | 11/20/2023 | Not Ready for Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 11/20/2023 | SGSOV Not Ready | MICHEL ABAJAN |
| Final | 12/19/2023 | Corrections Issued | JOHN HAYES |
| Green Building Final | 12/19/2023 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 12/19/2023 | SGSOV Not Ready | JOHN HAYES |
| Smoke Detectors | 12/19/2023 | Approved | JOHN HAYES |
| Final | 1/3/2024 | OK to Issue CofO | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 1/3/2024 | SGSOV Approved | JOHN HAYES |