11611 W LULL ST 91605

Certificate Information: 11611 W LULL ST 91605

Application / Permit
23016-20000-00282
Plan Check / Job No.
B22VN19258
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: CONVERT (E) GARAGE TO 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 1/19/2024
Issuing Office
Current Status
CofO Issued on 2/3/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/4/2023 APPLICANT
Assigned to Plan Check Engineer 1/11/2023 PRANITA SHAH
Corrections Issued 1/11/2023 PRANITA SHAH
Applicant returned to address corrections 1/16/2024 ARSALAN SHABESTARI
Plan Check Approved 1/18/2024 DANIEL YIP
Issued 1/19/2024 APPLICANT
CofO in Progress 1/12/2026 MATTHEW NELSON
Permit Finaled 2/3/2026 RUBEN SALAS
Permit Finaled 2/3/2026 RUBEN SALAS
CofO Issued 2/3/2026 RUBEN SALAS

Permit Application Clearance Information

Clean Up Green Up Cleared 4/20/2023 DANG NGUYEN
Construction near power lines Cleared 7/5/2023 RIDWAN HARDY
Address approval Cleared 7/19/2023 RYAN KIM
Eng Process Fee Ord 176,300 Cleared 7/19/2023 RYAN KIM
Roof/Waste drainage to street Cleared 7/19/2023 RYAN KIM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/30/2024 Partial Inspection MATTHEW NELSON
PLUMBING-Rough 3/8/2024 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 4/11/2024 Partial Approval MATTHEW NELSON
PLUMBING-Rough 4/11/2024 Partial Approval MATTHEW NELSON
Deputy Drilled-In Anchors 5/13/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 5/15/2024 Approved MATTHEW NELSON
ELECTRICAL-Rough 7/31/2024 Approved MATTHEW NELSON
PLUMBING-Rough 7/31/2024 Corrections Issued MATTHEW NELSON
Wood Frame 7/31/2024 Corrections Issued MATTHEW NELSON
BUILDING-Rough-Frame 8/2/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Rough-Elec/Plmb/HVAC 8/2/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Wood Frame 8/2/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 8/14/2024 Approved MATTHEW NELSON
Green Building Rough 8/14/2024 Approved MATTHEW NELSON
Insulation 8/14/2024 Approved MATTHEW NELSON
Interior/Exterior Lathing 8/14/2024 Approved MATTHEW NELSON
Drywall Nailing 9/13/2024 Approved MATTHEW NELSON
HVAC-Rough 9/13/2024 Approved MATTHEW NELSON
Interior/Exterior Lathing 9/13/2024 Approved MATTHEW NELSON
Shower Pan 9/13/2024 Approved MATTHEW NELSON
Final 11/19/2024 Corrections Issued MATTHEW NELSON
Green Building Final 11/19/2024 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 11/19/2024 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 11/19/2024 Approved MATTHEW NELSON
Final 1/8/2026 OK to Issue CofO MATTHEW NELSON
Green Building Final 1/8/2026 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 1/8/2026 SGSOV Approved MATTHEW NELSON