9637 N LANGDON AVE 91343
Certificate Information: 9637 N LANGDON AVE 91343
- Application / Permit
- 23016-20000-00066
- Plan Check / Job No.
- B22VN19225
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN- CONVERT 818 SF EXISTING DETACHED GARAGE TO ADU
- Permit Issued
- Issued on 3/2/2025
- Issuing Office
- Current Status
- Issued on 3/2/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/6/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2023 | MINA HABILI |
| Corrections Issued | 1/17/2023 | MINA HABILI |
| Plan Check Approved | 3/12/2023 | KHUONG TRUONG |
| Issued | 3/2/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/8/2023 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2023 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/8/2023 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Xi,, Wang; Lic. No.: NA85148 | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/1/2025 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 5/1/2025 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 5/1/2025 | Partial Approval | VINCENT HANLEY |
| Deputy Drilled-In Anchors | 5/9/2025 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 5/15/2025 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 5/23/2025 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 5/23/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 5/23/2025 | Not Ready for Inspection | VINCENT HANLEY |
| MERV13>=Rough | 5/23/2025 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 5/23/2025 | Approved | VINCENT HANLEY |
| Shower Pan | 5/23/2025 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 6/4/2025 | Approved | VINCENT HANLEY |
| Green Building Rough | 6/4/2025 | Approved | VINCENT HANLEY |
| HVAC-Rough | 6/4/2025 | Approved | VINCENT HANLEY |
| Insulation | 6/4/2025 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 6/4/2025 | Approved | VINCENT HANLEY |
| MERV13>=Rough | 6/4/2025 | Approved | VINCENT HANLEY |
| Underground Mechanical | 6/4/2025 | Partial Approval | VINCENT HANLEY |