9884-9886 N TAMARACK AVE 91331

Certificate Information: 9884-9886 N TAMARACK AVE 91331

Application / Permit
23016-20000-00033
Plan Check / Job No.
B22VN19211
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan Convert 500 sf of the (E) family room of the main house into a (N) JADU (500SQFT). PER STATE LAW NO SQFT ADDED, ALL WORK DONE PER WFPP
Permit Issued
Issued on 3/6/2023
Issuing Office
Current Status
CofO Issued on 3/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/2/2023 APPLICANT
Assigned to Plan Check Engineer 1/6/2023 KHUONG TRUONG
Corrections Issued 1/8/2023 KHUONG TRUONG
Plan Check Approved 2/15/2023 KHUONG TRUONG
Issued 3/6/2023 APPLICANT
CofO in Progress 2/2/2024 MICHEL ABAJAN
Permit Finaled 3/22/2024 RUBEN SALAS
CofO Issued 3/22/2024 RUBEN SALAS
Permit Finaled 3/22/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/18/2023 JOSE DUARTE-DIAZ
Sewer availability Cleared 1/18/2023 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 1/19/2023 JOSE DUARTE-DIAZ
Public Works-Highway Ded. Cleared 1/19/2023 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

HVAC-Rough 5/22/2023 Not Ready for Inspection JUAN VALENZUELA
Pre-Inspection 5/22/2023 Approved JUAN VALENZUELA
HVAC-Final 6/14/2023 No Access for Inspection JUAN VALENZUELA
PLUMBING-Final 6/14/2023 No Access for Inspection JUAN VALENZUELA
HVAC-Rough 6/20/2023 Approved MICHEL ABAJAN
PLUMBING-Rough 6/20/2023 Approved MICHEL ABAJAN
ELECTRICAL-Final 8/10/2023 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 9/28/2023 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 11/27/2023 Approved MICHEL ABAJAN
ELECTRICAL-Rough 11/27/2023 Approved MICHEL ABAJAN
Final 11/27/2023 Not Ready for Inspection MICHEL ABAJAN
HVAC-Rough 11/27/2023 Approved MICHEL ABAJAN
PLUMBING-Final 11/27/2023 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 11/27/2023 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 11/27/2023 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Final 1/10/2024 No Access for Inspection MICHEL ABAJAN
Final 1/10/2024 No Access for Inspection MICHEL ABAJAN
HVAC-Final 1/10/2024 No Access for Inspection MICHEL ABAJAN
PLUMBING-Final 1/10/2024 No Access for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/10/2024 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 1/10/2024 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Final 1/12/2024 Approved MICHEL ABAJAN
Final 1/12/2024 Corrections Issued MICHEL ABAJAN
HVAC-Final 1/12/2024 Approved MICHEL ABAJAN
PLUMBING-Final 1/12/2024 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/12/2024 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 1/12/2024 Not Ready for Inspection MICHEL ABAJAN
Final 2/2/2024 OK to Issue CofO MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 2/2/2024 SGSOV Approved MICHEL ABAJAN
Smoke Detectors 2/2/2024 Approved MICHEL ABAJAN