5865 S CAMPUS CENTER DR 90094
Certificate Information: 5865 S CAMPUS CENTER DR 90094
- Application / Permit
- 23016-10002-22087
- Plan Check / Job No.
- B24LA35096
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- SUPPLEMENTAL PERMIT TO 23016-10000-22087 TENANT IMPROVEMENT WITH ADDITIONAL DISTRIBUTION OF 8 PREFABRICATED PHONE BOOTHS (13 SF EACH) THROUGHOUT LEVELS 1,2,3 AND 4.
- Permit Issued
- Issued on 8/27/2025
- Issuing Office
- Current Status
- Issued on 8/27/2025
Permit Application Status History
| Submitted | 12/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 12/12/2024 | ARMEN JIVALAGIAN |
| Corrections Issued | 12/23/2024 | ARMEN JIVALAGIAN |
| Quality Review Completed | 12/26/2024 | PETER KIM |
| Applicant returned to address corrections | 7/17/2025 | ARMEN JIVALAGIAN |
| Plan Check Approved | 8/5/2025 | ARMEN JIVALAGIAN |
| Issued | 8/27/2025 | APPLICANT |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 12/31/2024 | MELISSA JONES |
| Green Code | Cleared | 1/10/2025 | ARMEN JIVALAGIAN |
| Fire Marshal Fire Life Safety | Cleared | 2/16/2025 | FIRE DEPARTMENT |
| DAS Clearance | Cleared | 2/19/2025 | ARMEN JIVALAGIAN |
Contact Information
| Architect | Hyman,, Ted Alan; Lic. No.: C14702 | 515 S FLOWER STREET SUITE 3700 LOS ANGELES, CA 90071 |
| Contractor | The Whiting-Turner Contracting Company; Lic. No.: 311107-B | , |
| Contractor | Whiting-Turner Contracting Company The; Lic. No.: 311107-B | , |
| Engineer | Pallmann,, Robert; Lic. No.: S6358 | 900 WILSHIRE BLVD 19TH FLOOR LOS ANGELES, CA 90017 |
Inspector Information
| DANIEL ARMENTA, (310) 914-3925 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 10/13/2025 | Not Ready for Inspection | VASIL MIHALEV |
| Drywall Nailing | 10/13/2025 | Off-Hour Fees Due | |
| Green Building Rough | 10/13/2025 | Off-Hour Fees Due | |
| Light Gage Steel Frame | 10/13/2025 | Not Ready for Inspection | VASIL MIHALEV |
| Light Gage Steel Frame | 10/13/2025 | Off-Hour Fees Due | |
| Pre-Inspection | 10/13/2025 | Not Ready for Inspection | VASIL MIHALEV |
| Pre-Inspection | 10/13/2025 | Off-Hour Fees Due | |
| Deputy Drilled-In Anchors | 10/14/2025 | Partial Approval | VASIL MIHALEV |
| Drywall Nailing | 10/14/2025 | Off-Hour Fees Due | |
| Green Building Rough | 10/14/2025 | Off-Hour Fees Due | |
| Light Gage Steel Frame | 10/14/2025 | Off-Hour Fees Due | |
| Pre-Inspection | 10/14/2025 | Off-Hour Fees Due | |
| Drywall Nailing | 11/12/2025 | Approved | VASIL MIHALEV |
| Deputy Drilled-In Anchors | 11/26/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Drilled-In Anchors | 12/1/2025 | Approved | VASIL MIHALEV |
| Deputy Drilled-In Anchors | 12/2/2025 | Partial Approval | VASIL MIHALEV |
| Deputy Drilled-In Anchors | 1/6/2026 | Partial Approval | VASIL MIHALEV |
| Drywall Nailing | 1/28/2026 | Approved | VASIL MIHALEV |
| Light Gage Steel Frame | 2/11/2026 | Off-Hour Fees Due | |
| Light Gage Steel Frame | 2/11/2026 | Partial Approval | FARHAD DADBIN |
| Drywall Nailing | 2/25/2026 | Partial Approval | FARHAD DADBIN |
| Deputy Drilled-In Anchors | 4/8/2026 | Conditional Approval | DANIEL ARMENTA |
| Drywall Nailing | 4/8/2026 | Partial Approval | DANIEL ARMENTA |
| Deputy Drilled-In Anchors | 4/9/2026 | Conditional Approval | DANIEL ARMENTA |
| Deputy Drilled-In Anchors | 4/14/2026 | Approved | DERRICK SPENCER |
| Deputy Drilled-In Anchors | 4/15/2026 | Conditional Approval | DANIEL ARMENTA |
| Deputy Drilled-In Anchors | 4/16/2026 | Conditional Approval | DANIEL ARMENTA |
| Light Gage Steel Frame | 4/23/2026 | Not Ready for Inspection | FARHAD DADBIN |
| Light Gage Steel Frame | 4/28/2026 | Not Ready for Inspection | DANIEL ARMENTA |
| Final | 6/11/2026 | Not Ready for Inspection | DANIEL ARMENTA |
| Green Building Final | 6/11/2026 | Not Ready for Inspection | DANIEL ARMENTA |
| Smoke Detectors | 6/11/2026 | Approved | DANIEL ARMENTA |