924-924 1/2 E 46TH ST 90011

Certificate Information: 924-924 1/2 E 46TH ST 90011

Application / Permit
23016-10001-21031
Plan Check / Job No.
B24LA07342
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
SUPPLEMENTAL TO 23016-20000-21031 TO CAPTURE MEP CHECKLIST ITEMS AND FEES
Permit Issued
Issued on 4/19/2024
Issuing Office
Metro
Current Status
Permit Finaled on 6/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Plan Check Approved 4/19/2024 JOSEPH RAFOLS
Issued 4/19/2024 APPLICANT
Permit Finaled 6/24/2025 ALEJANDRO DE ARTOLA

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 4/29/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 4/29/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 4/29/2024 Approved ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 5/7/2024 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 5/7/2024 Approved ALEJANDRO DE ARTOLA
Insulation 5/14/2024 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 5/21/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 6/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
Final 6/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 6/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 6/24/2024 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Final 7/8/2024 Approved ALEJANDRO DE ARTOLA
Final 7/8/2024 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 7/8/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 7/8/2024 Approved ALEJANDRO DE ARTOLA
Final 7/26/2024 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 7/26/2024 Approved ALEJANDRO DE ARTOLA
Pre-Inspection 9/10/2024 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 10/1/2024 Approved ALEJANDRO DE ARTOLA
Wood Frame 10/1/2024 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 10/3/2024 Approved ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 1/14/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 1/21/2025 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 1/28/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 1/28/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 1/28/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 2/5/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 2/5/2025 Approved ALEJANDRO DE ARTOLA
Rough-Elec/Plmb/HVAC 2/5/2025 Approved ALEJANDRO DE ARTOLA
Wood Frame 2/5/2025 Approved ALEJANDRO DE ARTOLA
Insulation 2/7/2025 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 2/7/2025 Partial Approval ALEJANDRO DE ARTOLA
Drywall Nailing 3/3/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 6/24/2025 Approved ALEJANDRO DE ARTOLA
Final 6/24/2025 Permit Finaled ALEJANDRO DE ARTOLA
HVAC-Final 6/24/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 6/24/2025 Approved ALEJANDRO DE ARTOLA