1514-1514 1/2 E PENNSYLVANIA AVE 90033

Certificate Information: 1514-1514 1/2 E PENNSYLVANIA AVE 90033

Application / Permit
23016-10001-11238
Plan Check / Job No.
B24LA04446
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Supplemental to 23016-10000-11238 to revise the scope of work to : " New 2-Story, 2-Unit Accessory Dwelling Unit Building Per State Law with Attached Garage and Storage . Garage and Storage at 1st Floor . Accessory Dwelling Units at 2nd Floor . " "COMPLY WITH DEPARTMENT ORDER effective date 09/09/2022. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 7/1/2024
Issuing Office
Current Status
Permit Finaled on 9/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2024 APPLICANT
Assigned to Plan Check Engineer 3/15/2024 GEORGE ALVAREZ
Corrections Issued 3/18/2024 GEORGE ALVAREZ
Applicant returned to address corrections 4/30/2024 JOSEPH RAFOLS
Plan Check Approved 6/30/2024 JOSEPH RAFOLS
Issued 7/1/2024 APPLICANT
Permit Finaled 9/9/2025 ALIZAH MAYAGOITIA

Permit Application Clearance Information

Address approval Cleared 3/26/2024 WALLIE JONG
Clean Up Green Up Cleared 3/26/2024 STEVEN WECHSLER
Sewer availability Cleared 3/26/2024 WALLIE JONG
ZI Cleared 3/26/2024 STEVEN WECHSLER
Work Adjacent to Public Way Cleared 3/27/2024 JOSE RODRIGUEZ
Eng Process Fee Ord 176,300 Cleared 3/28/2024 WALLIE JONG
Historic monument Cleared 3/28/2024 RAFAEL FONTES
Construction near power lines Cleared 4/3/2024 WALTER RAMIREZ
Construction within easement Cleared 4/3/2024 WALTER RAMIREZ
Tenant Habitability Plan Cleared 4/17/2024 HUGO GARRIDO GARZA
Grading Pre-Inspection Cleared 4/30/2024 GEORGE ALVAREZ
Low Impact Development (LID) Cleared 6/27/2024 LUIS LUVANO

Contact Information

Contractor T & E Builders Inc; Lic. No.: 1044967-B       ,
Engineer Kazemi,, Milad; Lic. No.: C92143 28025 DOROTHY DR STE 202      AGOURA HILLS, CA 91301

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/26/2024 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 10/31/2024 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 10/31/2024 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 11/15/2024 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 11/15/2024 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 1/14/2025 Partial Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 1/23/2025 Approved OSVALDO PARAMO
Footing/Foundation/Slab 1/23/2025 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 2/12/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 2/12/2025 Partial Approval ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 2/24/2025 Partial Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 3/7/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 4/15/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 4/18/2025 Approved ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 4/18/2025 Approved ALIZAH MAYAGOITIA
HVAC-Rough 4/18/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 4/28/2025 Approved ALIZAH MAYAGOITIA
Green Building Rough 4/28/2025 Approved ALIZAH MAYAGOITIA
MERV13>=Rough 4/28/2025 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 4/28/2025 Approved ALIZAH MAYAGOITIA
Insulation 5/2/2025 Approved ANTHONY RAMOS
Interior/Exterior Lathing 5/2/2025 Partial Approval ANTHONY RAMOS
Floor/Roof Diaphrgm/Shear Wall 5/5/2025 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 5/9/2025 Approved ALIZAH MAYAGOITIA
Drywall Nailing 5/20/2025 Corrections Issued ANTHONY RAMOS
Drywall Nailing 5/28/2025 Approved REGINA MENDEZ
Pre-Inspection 7/15/2025 Approved JUSTIN HAWLEY
Service/Power Release 7/18/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Final 7/30/2025 Approved ALIZAH MAYAGOITIA
Final 8/5/2025 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 8/5/2025 Approved ALIZAH MAYAGOITIA
Green Building Final 8/5/2025 Approved ALIZAH MAYAGOITIA
MERV13>=Final 8/5/2025 Approved ALIZAH MAYAGOITIA
Service/Power Release 8/5/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 8/5/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 9/2/2025 Approved ALIZAH MAYAGOITIA
Final 9/2/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Service/Power Release 9/2/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 9/9/2025 Permit Finaled ALIZAH MAYAGOITIA
Service/Power Release 9/9/2025 Approved ALIZAH MAYAGOITIA