1860 N WESTERN AVE STE 101 90027
Certificate Information: 1860 N WESTERN AVE STE 101 90027
- Application / Permit
- 23016-10001-02894
- Plan Check / Job No.
- B24LA17219
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Office
- Work Description
- Eplan. Supplemental permit to 23016-10000-02894 to clarify medical office size (3995 sf) and change of occupancy from retail to medical office.
- Permit Issued
- Issued on 9/9/2024
- Issuing Office
- Current Status
- CofO Issued on 3/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/9/2024 | ADAM HEGAZI |
| Corrections Issued | 8/9/2024 | ADAM HEGAZI |
| Plan Check Approved | 9/6/2024 | SAMUEL GONZALEZ |
| Issued | 9/9/2024 | APPLICANT |
| TCO Issued (Expire Date: 04-07-2025) | 10/9/2024 | ERNESTO CORRAL |
| CofO in Progress | 3/11/2025 | LUIS CCAMACHO |
| Permit Finaled | 3/11/2025 | ERNESTO CORRAL |
| CofO Issued | 3/11/2025 | ERNESTO CORRAL |
| Permit Finaled | 3/11/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| CPC | Cleared | 8/13/2024 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 8/13/2024 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 8/13/2024 | JAZMIN ROQUE |
| Miscellaneous | Cleared | 8/13/2024 | JAZMIN ROQUE |
| ZA Case | Cleared | 8/13/2024 | JAZMIN ROQUE |
| ZI | Cleared | 8/13/2024 | JAZMIN ROQUE |
| Eng Process Fee Ord 176,300 | Cleared | 9/5/2024 | JEANIE LAM |
| Sewer availability | Cleared | 9/5/2024 | JEANIE LAM |
| Specific Plan | Cleared | 9/5/2024 | YAMILLET BRIZUELA |
Contact Information
| Contractor | Jlc Associates Inc; Lic. No.: 645576-B | , |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 9/10/2024 | Not Ready for Inspection | RAFAEL CORTES |
| Reinforced Concrete Frame | 9/10/2024 | No Access for Inspection | RAFAEL CORTES |
| Final | 10/2/2024 | Partial Inspection | TIMOTHY POWELL |
| Reinforced Concrete Frame | 10/2/2024 | Approved | TIMOTHY POWELL |
| Special/Order Compliance | 3/4/2025 | Partial Inspection | LUIS CCAMACHO |
| Final | 3/11/2025 | OK to Issue CofO | LUIS CCAMACHO |
| Special/Order Compliance | 3/11/2025 | Partial Approval | LUIS CCAMACHO |