5206 N FIGUEROA ST 90042

Certificate Information: 5206 N FIGUEROA ST 90042

Application / Permit
23016-10001-00011
Plan Check / Job No.
B23LA12303
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(6) Church
Work Description
(epLan) Supplemental to Permit #23016-10000-00011 to include seismic retrofit.
Permit Issued
Issued on 12/1/2023
Issuing Office
Current Status
Permit Finaled on 1/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/6/2023 APPLICANT
Assigned to Plan Check Engineer 7/13/2023 YOUNG KIM
Corrections Issued 8/1/2023 YOUNG KIM
Quality Review Completed 8/8/2023 FARUK SEZER
Applicant returned to address corrections 8/10/2023 YOUNG KIM
Applicant returned to address corrections 9/14/2023 YOUNG KIM
Applicant returned to address corrections 9/26/2023 YOUNG KIM
Applicant returned to address corrections 11/21/2023 SAM CHANG
Plan Check Approved 11/30/2023 SAM CHANG
Issued 12/1/2023 APPLICANT
Permit Finaled-Status Void 1/15/2025 RAMAZANALI ALMASI
Re-Activate Permit 1/27/2025 RAMAZANALI ALMASI
Permit Finaled 1/27/2025 RAMAZANALI ALMASI

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Kluger,, Charles Edward; Lic. No.: NA24283       ,
Contractor Renault And Moran Construction Llc; Lic. No.: 1038156-B       ,
Engineer Hodali,, Ramzi; Lic. No.: S3552 3830 DIXIE CANYON AVE      SHERMAN OAKS, CA 91423

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/5/2023 Partial Approval RAMAZANALI ALMASI
Footing/Foundation/Slab 12/5/2023 Partial Approval RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 12/12/2023 Partial Approval RAFAEL CORTES
Footing/Foundation/Slab 12/12/2023 Not Ready for Inspection RAFAEL CORTES
Masonry Wall/Backfill 12/19/2023 Partial Approval RAMAZANALI ALMASI
Pre-Inspection 12/21/2023 Approved RAFAEL CORTES
Masonry Wall/Backfill 12/27/2023 Partial Approval RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 1/2/2024 Partial Approval RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 1/8/2024 Not Ready for Inspection RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 1/10/2024 Partial Approval RAMAZANALI ALMASI
Footing/Foundation/Slab 1/10/2024 Partial Approval RAMAZANALI ALMASI
Excavation/Setback/Form/Re-Bar 1/17/2024 Conditional Approval DARRYL ARNOLD
Deputy Drilled-In Anchors 2/7/2024 Conditional Approval RONALD JIMENEZ
Floor/Roof Diaphrgm/Shear Wall 2/7/2024 Partial Approval RONALD JIMENEZ
Wood Frame 2/7/2024 Partial Approval RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 2/8/2024 Approved RAMAZANALI ALMASI
Deputy Steel/Welding 2/16/2024 Conditional Approval MICHAEL ROSENBERG
Footing/Foundation/Slab 3/13/2024 Partial Approval RONALD JIMENEZ
Light Gage Steel Frame 3/13/2024 Approved RONALD JIMENEZ
Wood Frame 3/13/2024 Not Ready for Inspection RONALD JIMENEZ
Interior/Exterior Lathing 5/22/2024 Approved RAMAZANALI ALMASI
Final 6/13/2024 Not Ready for Inspection RAMAZANALI ALMASI
Green Building Final 6/13/2024 Not Ready for Inspection RAMAZANALI ALMASI
Smoke Detectors 6/13/2024 Not Ready for Inspection RAMAZANALI ALMASI
Structural Steel Frame 6/13/2024 Not Ready for Inspection RAMAZANALI ALMASI
Final 9/11/2024 Not Ready for Inspection RAMAZANALI ALMASI
Green Building Final 9/11/2024 Not Ready for Inspection RAMAZANALI ALMASI
Green Building Rough 9/11/2024 Not Ready for Inspection RAMAZANALI ALMASI
Smoke Detectors 9/11/2024 Not Ready for Inspection RAMAZANALI ALMASI
Final 12/6/2024 Conditional Approval RAMAZANALI ALMASI
Green Building Final 12/6/2024 Approved RAMAZANALI ALMASI
Smoke Detectors 12/6/2024 Approved RAMAZANALI ALMASI
Final 1/15/2025 Partial Inspection RAMAZANALI ALMASI