5985 W CENTURY BLVD 90045
Certificate Information: 5985 W CENTURY BLVD 90045
- Application / Permit
- 23016-10000-45016
- Plan Check / Job No.
- B23LA24284
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (11) Hotel
- Work Description
- Commercial TI (remodel) of an existing hotel. Guestroom Renovation to 614 hotel rooms, including 610 existing guestrooms, 1 new guestroom and 3 existing parlors. Scope includes replacement of existing finishes, fixtures, and light fixtures. Modifications to improve the existing ADA mix and configuration are included.
- Permit Issued
- Issued on 5/15/2024
- Issuing Office
- Current Status
- Permit Finaled on 4/3/2025
Permit Application Status History
| Submitted | 1/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/11/2024 | JOE VO |
| Corrections Issued | 1/14/2024 | JOE VO |
| Assigned to Zoning Architect | 1/18/2024 | JOE VO |
| Quality Review Completed | 1/18/2024 | PRANITA SHAH |
| Applicant returned to address corrections | 2/8/2024 | JOE VO |
| Plan Check Approved | 5/13/2024 | JOE VO |
| Issued | 5/15/2024 | APPLICANT |
| Permit Finaled | 4/3/2025 | RICARDO ROBLES |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 2/26/2024 | CAELAN RAFFERTY |
| Fire Marshal Fire Life Safety | Cleared | 3/18/2024 | WILLIAM JOHNS |
| Green Code | Cleared | 4/11/2024 | AARON COSTA |
| DAS Clearance | Cleared | 4/25/2024 | Gurunath Nesarajah |
| Zoning Plan Check | Cleared | 5/13/2024 | Gurunath Nesarajah |
Contact Information
| Contractor | First Finish Inc; Lic. No.: 981707-B | , |
| Contractor | First Finish Llc; Lic. No.: 981707-B | , |
Inspector Information
| DANIEL ARMENTA, (310) 914-3925 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/30/2024 | Partial Approval | RICARDO ROBLES |
| Insulation | 6/5/2024 | Approved | MICHAEL PETRUSKO |
| Light Gage Steel Frame | 6/5/2024 | Approved | MICHAEL PETRUSKO |
| Drywall Nailing | 6/11/2024 | Partial Approval | RICARDO ROBLES |
| Insulation | 6/11/2024 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 6/11/2024 | Partial Approval | RICARDO ROBLES |
| Insulation | 6/25/2024 | Partial Approval | GRANT WOODS |
| Light Gage Steel Frame | 6/25/2024 | Partial Approval | GRANT WOODS |
| Drywall Nailing | 7/1/2024 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 7/9/2024 | Partial Approval | RICARDO ROBLES |
| Insulation | 7/23/2024 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 7/23/2024 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 8/2/2024 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 8/6/2024 | Partial Approval | RICARDO ROBLES |
| Green Building Final | 8/19/2024 | Not Ready for Inspection | RICARDO ROBLES |
| Pre-Inspection | 8/19/2024 | Partial Approval | RICARDO ROBLES |
| SGSOV-Seismic Gas S/O Valve | 8/19/2024 | SGSOV Not Ready | RICARDO ROBLES |
| Smoke Detectors | 8/19/2024 | Not Ready for Inspection | RICARDO ROBLES |
| Drywall Nailing | 8/23/2024 | Partial Approval | RICARDO ROBLES |
| Interior/Exterior Lathing | 8/23/2024 | Partial Approval | RICARDO ROBLES |
| Pre-Inspection | 8/28/2024 | Partial Approval | RICARDO ROBLES |
| Final | 9/4/2024 | Partial Approval | DAVID TSAU |
| Green Building Final | 9/4/2024 | Partial Approval | DAVID TSAU |
| SGSOV-Seismic Gas S/O Valve | 9/4/2024 | SGSOV Not Ready | DAVID TSAU |
| Smoke Detectors | 9/4/2024 | Partial Approval | DAVID TSAU |
| Final | 9/17/2024 | Not Ready for Inspection | GRANT WOODS |
| Green Building Final | 9/17/2024 | Approved | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 9/17/2024 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 9/17/2024 | Approved | GRANT WOODS |
| Light Gage Steel Frame | 9/18/2024 | Partial Approval | GRANT WOODS |
| Drywall Nailing | 9/24/2024 | Partial Approval | GRANT WOODS |
| Final | 9/24/2024 | Not Ready for Inspection | GRANT WOODS |
| Final | 9/30/2024 | Partial Approval | GRANT WOODS |
| Drywall Nailing | 10/28/2024 | Partial Approval | GRANT WOODS |
| Wall Anchors | 10/31/2024 | Approved | MICHAEL PETRUSKO |
| Final | 11/5/2024 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 11/5/2024 | Partial Approval | RICARDO ROBLES |
| Pre-Inspection | 11/6/2024 | Not Ready for Inspection | GRANT WOODS |
| Drywall Nailing | 11/8/2024 | Partial Approval | RICARDO ROBLES |
| Final | 11/8/2024 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 11/13/2024 | Corrections Issued | RICARDO ROBLES |
| Drywall Nailing | 11/14/2024 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 11/15/2024 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 11/18/2024 | Partial Approval | RICARDO ROBLES |
| Final | 11/19/2024 | Not Ready for Inspection | RICARDO ROBLES |
| Final | 11/26/2024 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 11/27/2024 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 12/2/2024 | Partial Approval | RICARDO ROBLES |
| Final | 12/2/2024 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 12/9/2024 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 12/17/2024 | Partial Approval | MICHAEL PETRUSKO |
| Drywall Nailing | 12/23/2024 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 1/9/2025 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 1/9/2025 | Partial Approval | RICARDO ROBLES |
| Final | 1/14/2025 | Not Ready for Inspection | RICARDO ROBLES |
| Drywall Nailing | 1/16/2025 | Partial Approval | RICARDO ROBLES |
| Final | 1/16/2025 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 1/22/2025 | Partial Inspection | AMANUEL BERHE |
| Light Gage Steel Frame | 1/22/2025 | Approved | AMANUEL BERHE |
| Drywall Nailing | 1/24/2025 | Partial Approval | RICARDO ROBLES |
| Wall Anchors | 1/24/2025 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 1/28/2025 | Partial Approval | RICARDO ROBLES |
| Final | 1/28/2025 | Partial Approval | RICARDO ROBLES |
| Final | 2/12/2025 | Partial Approval | RICARDO ROBLES |
| Final | 2/21/2025 | Not Ready for Inspection | AMANUEL BERHE |
| Pre-Inspection | 2/25/2025 | Partial Approval | RICARDO ROBLES |
| Final | 3/6/2025 | Partial Approval | RICARDO ROBLES |
| Final | 3/21/2025 | Not Ready for Inspection | RICARDO ROBLES |
| Final | 3/25/2025 | Partial Approval | RICARDO ROBLES |
| Final | 3/28/2025 | Partial Approval | RICARDO ROBLES |
| Final | 4/3/2025 | Permit Finaled | RICARDO ROBLES |