5985 W CENTURY BLVD 90045

Certificate Information: 5985 W CENTURY BLVD 90045

Application / Permit
23016-10000-45016
Plan Check / Job No.
B23LA24284
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(11) Hotel
Work Description
Commercial TI (remodel) of an existing hotel. Guestroom Renovation to 614 hotel rooms, including 610 existing guestrooms, 1 new guestroom and 3 existing parlors. Scope includes replacement of existing finishes, fixtures, and light fixtures. Modifications to improve the existing ADA mix and configuration are included.
Permit Issued
Issued on 5/15/2024
Issuing Office
Current Status
Permit Finaled on 4/3/2025

Permit Application Status History

Submitted 1/10/2024 APPLICANT
Assigned to Plan Check Engineer 1/11/2024 JOE VO
Corrections Issued 1/14/2024 JOE VO
Assigned to Zoning Architect 1/18/2024 JOE VO
Quality Review Completed 1/18/2024 PRANITA SHAH
Applicant returned to address corrections 2/8/2024 JOE VO
Plan Check Approved 5/13/2024 JOE VO
Issued 5/15/2024 APPLICANT
Permit Finaled 4/3/2025 RICARDO ROBLES

Permit Application Clearance Information

Community Plan Implem. Overlay Cleared 2/26/2024 CAELAN RAFFERTY
Fire Marshal Fire Life Safety Cleared 3/18/2024 WILLIAM JOHNS
Green Code Cleared 4/11/2024 AARON COSTA
DAS Clearance Cleared 4/25/2024 Gurunath Nesarajah
Zoning Plan Check Cleared 5/13/2024 Gurunath Nesarajah

Contact Information

Contractor First Finish Inc; Lic. No.: 981707-B       ,
Contractor First Finish Llc; Lic. No.: 981707-B       ,

Inspector Information

DANIEL ARMENTA, (310) 914-3925 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/30/2024 Partial Approval RICARDO ROBLES
Insulation 6/5/2024 Approved MICHAEL PETRUSKO
Light Gage Steel Frame 6/5/2024 Approved MICHAEL PETRUSKO
Drywall Nailing 6/11/2024 Partial Approval RICARDO ROBLES
Insulation 6/11/2024 Partial Approval RICARDO ROBLES
Light Gage Steel Frame 6/11/2024 Partial Approval RICARDO ROBLES
Insulation 6/25/2024 Partial Approval GRANT WOODS
Light Gage Steel Frame 6/25/2024 Partial Approval GRANT WOODS
Drywall Nailing 7/1/2024 Partial Approval RICARDO ROBLES
Drywall Nailing 7/9/2024 Partial Approval RICARDO ROBLES
Insulation 7/23/2024 Partial Approval RICARDO ROBLES
Light Gage Steel Frame 7/23/2024 Partial Approval RICARDO ROBLES
Drywall Nailing 8/2/2024 Partial Approval RICARDO ROBLES
Drywall Nailing 8/6/2024 Partial Approval RICARDO ROBLES
Green Building Final 8/19/2024 Not Ready for Inspection RICARDO ROBLES
Pre-Inspection 8/19/2024 Partial Approval RICARDO ROBLES
SGSOV-Seismic Gas S/O Valve 8/19/2024 SGSOV Not Ready RICARDO ROBLES
Smoke Detectors 8/19/2024 Not Ready for Inspection RICARDO ROBLES
Drywall Nailing 8/23/2024 Partial Approval RICARDO ROBLES
Interior/Exterior Lathing 8/23/2024 Partial Approval RICARDO ROBLES
Pre-Inspection 8/28/2024 Partial Approval RICARDO ROBLES
Final 9/4/2024 Partial Approval DAVID TSAU
Green Building Final 9/4/2024 Partial Approval DAVID TSAU
SGSOV-Seismic Gas S/O Valve 9/4/2024 SGSOV Not Ready DAVID TSAU
Smoke Detectors 9/4/2024 Partial Approval DAVID TSAU
Final 9/17/2024 Not Ready for Inspection GRANT WOODS
Green Building Final 9/17/2024 Approved GRANT WOODS
SGSOV-Seismic Gas S/O Valve 9/17/2024 SGSOV Approved GRANT WOODS
Smoke Detectors 9/17/2024 Approved GRANT WOODS
Light Gage Steel Frame 9/18/2024 Partial Approval GRANT WOODS
Drywall Nailing 9/24/2024 Partial Approval GRANT WOODS
Final 9/24/2024 Not Ready for Inspection GRANT WOODS
Final 9/30/2024 Partial Approval GRANT WOODS
Drywall Nailing 10/28/2024 Partial Approval GRANT WOODS
Wall Anchors 10/31/2024 Approved MICHAEL PETRUSKO
Final 11/5/2024 Partial Approval RICARDO ROBLES
Light Gage Steel Frame 11/5/2024 Partial Approval RICARDO ROBLES
Pre-Inspection 11/6/2024 Not Ready for Inspection GRANT WOODS
Drywall Nailing 11/8/2024 Partial Approval RICARDO ROBLES
Final 11/8/2024 Partial Approval RICARDO ROBLES
Drywall Nailing 11/13/2024 Corrections Issued RICARDO ROBLES
Drywall Nailing 11/14/2024 Partial Approval RICARDO ROBLES
Drywall Nailing 11/15/2024 Partial Approval RICARDO ROBLES
Drywall Nailing 11/18/2024 Partial Approval RICARDO ROBLES
Final 11/19/2024 Not Ready for Inspection RICARDO ROBLES
Final 11/26/2024 Partial Approval RICARDO ROBLES
Drywall Nailing 11/27/2024 Partial Approval RICARDO ROBLES
Drywall Nailing 12/2/2024 Partial Approval RICARDO ROBLES
Final 12/2/2024 Partial Approval RICARDO ROBLES
Light Gage Steel Frame 12/9/2024 Partial Approval RICARDO ROBLES
Drywall Nailing 12/17/2024 Partial Approval MICHAEL PETRUSKO
Drywall Nailing 12/23/2024 Partial Approval RICARDO ROBLES
Drywall Nailing 1/9/2025 Partial Approval RICARDO ROBLES
Light Gage Steel Frame 1/9/2025 Partial Approval RICARDO ROBLES
Final 1/14/2025 Not Ready for Inspection RICARDO ROBLES
Drywall Nailing 1/16/2025 Partial Approval RICARDO ROBLES
Final 1/16/2025 Partial Approval RICARDO ROBLES
Drywall Nailing 1/22/2025 Partial Inspection AMANUEL BERHE
Light Gage Steel Frame 1/22/2025 Approved AMANUEL BERHE
Drywall Nailing 1/24/2025 Partial Approval RICARDO ROBLES
Wall Anchors 1/24/2025 Partial Approval RICARDO ROBLES
Drywall Nailing 1/28/2025 Partial Approval RICARDO ROBLES
Final 1/28/2025 Partial Approval RICARDO ROBLES
Final 2/12/2025 Partial Approval RICARDO ROBLES
Final 2/21/2025 Not Ready for Inspection AMANUEL BERHE
Pre-Inspection 2/25/2025 Partial Approval RICARDO ROBLES
Final 3/6/2025 Partial Approval RICARDO ROBLES
Final 3/21/2025 Not Ready for Inspection RICARDO ROBLES
Final 3/25/2025 Partial Approval RICARDO ROBLES
Final 3/28/2025 Partial Approval RICARDO ROBLES
Final 4/3/2025 Permit Finaled RICARDO ROBLES