6050 W 75TH ST 90045
Certificate Information: 6050 W 75TH ST 90045
- Application / Permit
- 23016-10000-44970
- Plan Check / Job No.
- B23LA24261
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. CONVERT (E) GARAGE & STORAGE TO (N) ACCESSORY DWELLING UNIT PER STATE LAW
- Permit Issued
- Issued on 5/28/2024
- Issuing Office
- Current Status
- CofO Issued on 2/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/24/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2023 | JOHN MESIAS |
| Corrections Issued | 12/28/2023 | JOHN MESIAS |
| Plan Check Approved | 2/24/2024 | FERNANDO FLORES |
| No Progress | 3/8/2024 | FERNANDO FLORES |
| Plan Check Approved | 3/8/2024 | FERNANDO FLORES |
| No Progress | 5/6/2024 | FERNANDO FLORES |
| Plan Check Approved | 5/6/2024 | FERNANDO FLORES |
| Issued | 5/28/2024 | APPLICANT |
| CofO in Progress | 1/22/2025 | ANTHONY EGSON |
| Permit Finaled | 2/12/2025 | RICHARD STEINBACH |
| CofO Issued | 2/12/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/11/2024 | GERMAN RODRIGUEZ MENDO |
| Address approval | Cleared | 2/15/2024 | VLADIMIR ARUTYUNYAN |
| Specific Plan | Cleared | 2/21/2024 | FREDDY GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2024 | VLADIMIR ARUTYUNYAN |
| Sewer availability | Cleared | 2/22/2024 | VLADIMIR ARUTYUNYAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Chiu,, Ivan Wai-Kuen; Lic. No.: C44672 | 2160 PARNELL WY ALTADENA, CA 91001 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/8/2024 | Corrections Issued | RICHARD STEINBACH |
| Pre-Inspection | 8/9/2024 | No Access for Inspection | TEMISTOCLES CAAL |
| Sewer | 8/19/2024 | Approved | BOBBY KEY |
| Underground Mechanical | 8/19/2024 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 8/21/2024 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 8/22/2024 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 8/26/2024 | Not Ready for Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 8/30/2024 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 10/4/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 10/4/2024 | Approved | BOBBY KEY |
| HVAC-Rough | 10/4/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 10/4/2024 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 10/7/2024 | Corrections Issued | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 10/7/2024 | Partial Approval | ARAM AVEDISIAN |
| Insulation | 10/9/2024 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 10/15/2024 | Approved | BOBBY KEY |
| Green Building Rough | 10/15/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 10/15/2024 | Approved | BOBBY KEY |
| Shower Pan | 10/15/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 10/18/2024 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 12/10/2024 | SGSOV Not Ready | BOBBY KEY |
| Final | 12/24/2024 | Corrections Issued | MICHAEL ALLEN |
| Gas Test | 12/24/2024 | Approved | MICHAEL ALLEN |
| Green Building Final | 12/24/2024 | Approved | MICHAEL ALLEN |
| HVAC-Final | 12/24/2024 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 12/24/2024 | SGSOV Approved | MICHAEL ALLEN |
| Smoke Detectors | 12/24/2024 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 1/16/2025 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 1/16/2025 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 1/16/2025 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 1/21/2025 | Approved | ANTHONY EGSON |
| Final | 1/21/2025 | OK to Issue CofO | ANTHONY EGSON |