1007-1007 1/2 N AVENUE 51 90042

Certificate Information: 1007-1007 1/2 N AVENUE 51 90042

Application / Permit
23016-10000-44798
Plan Check / Job No.
B23LA24115
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
***EPLAN*** CONVERT (E) BASEMENT TO ADU PER LAMC 12.22 A.33(c) AND (e)
Permit Issued
Issued on 4/8/2024
Issuing Office
Current Status
CofO Issued on 2/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/4/2024 APPLICANT
Assigned to Plan Check Engineer 1/25/2024 YASHAR EMAMI
Corrections Issued 1/29/2024 YASHAR EMAMI
Re-Submittal Required 2/12/2024 REZA HAGHIGHAT
Re-Submitted 3/6/2024 YASHAR EMAMI
Corrections Issued 2 3/6/2024 YASHAR EMAMI
Submitted for Second Quality Review 3/6/2024 YASHAR EMAMI
Quality Review Completed 3/11/2024 REZA HAGHIGHAT
Plan Check Approved 4/5/2024 YASHAR EMAMI
Issued 4/8/2024 APPLICANT
CofO in Progress 10/25/2024 FERMIN RUBIO
Permit Finaled 2/6/2025 DANIEL SANCHEZ
CofO Issued 2/6/2025 DANIEL SANCHEZ
Permit Finaled 2/6/2025 DANIEL SANCHEZ

Permit Application Clearance Information

Address approval Cleared 3/11/2024 TREVOR QUAN
Sewer availability Cleared 3/11/2024 TREVOR QUAN
Street Frontage Cleared 3/11/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 3/12/2024 WALLIE JONG
Miscellaneous Cleared 3/14/2024 ALBERT TAM

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367
Engineer Sivushenka,, Mikita; Lic. No.: NA87698       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 5/22/2024 Partial Inspection COREY HUPP
Excavation/Setback/Form/Re-Bar 5/31/2024 Approved JONATHAN FRANCHINI
Floor/Roof Diaphrgm/Shear Wall 5/31/2024 Not Ready for Inspection JONATHAN FRANCHINI
BUILDING-Rough-Frame 7/29/2024 Not Ready for Inspection JACOB SEGURA
ELECTRICAL-Rough 7/29/2024 Approved JACOB SEGURA
Green Building Rough 7/29/2024 Not Ready for Inspection JACOB SEGURA
HVAC-Rough 7/29/2024 Not Ready for Inspection JACOB SEGURA
PLUMBING-Rough 7/29/2024 Partial Approval JACOB SEGURA
BUILDING-Rough-Frame 8/1/2024 Corrections Issued FERMIN RUBIO
Green Building Rough 8/1/2024 Corrections Issued FERMIN RUBIO
HVAC-Rough 8/1/2024 Corrections Issued FERMIN RUBIO
Insulation 8/1/2024 Corrections Issued FERMIN RUBIO
PLUMBING-Rough 8/1/2024 Corrections Issued FERMIN RUBIO
Insulation 8/5/2024 Partial Approval JACOB SEGURA
BUILDING-Rough-Frame 8/8/2024 Approved JACOB SEGURA
Drywall Nailing 8/8/2024 Approved JACOB SEGURA
Green Building Rough 8/8/2024 Approved JACOB SEGURA
Insulation 8/8/2024 Approved JACOB SEGURA
Interior/Exterior Lathing 8/8/2024 Approved JACOB SEGURA
PLUMBING-Rough 8/8/2024 Approved JACOB SEGURA
Shower Pan 8/8/2024 Approved JACOB SEGURA
Final 9/23/2024 Corrections Issued JACOB SEGURA
Green Building Final 9/23/2024 Corrections Issued JACOB SEGURA
SGSOV-Seismic Gas S/O Valve 9/23/2024 SGSOV Approved JACOB SEGURA
Smoke Detectors 9/23/2024 Approved JACOB SEGURA
Final 10/7/2024 Corrections Issued JACOB SEGURA
Green Building Final 10/7/2024 Approved JACOB SEGURA
Insulation 10/10/2024 Approved JACOB SEGURA
Pre-Inspection 10/10/2024 Approved JACOB SEGURA
Final 10/16/2024 Not Ready for Inspection FERMIN RUBIO
Final 10/18/2024 Conditional Approval FERMIN RUBIO
Final 10/22/2024 Conditional Approval FERMIN RUBIO
ELECTRICAL-Final 10/25/2024 Approved FERMIN RUBIO
Final 10/25/2024 OK to Issue CofO FERMIN RUBIO
HVAC-Final 10/25/2024 Approved FERMIN RUBIO
PLUMBING-Final 10/25/2024 Approved FERMIN RUBIO