427 E 111TH PL 90061

Certificate Information: 427 E 111TH PL 90061

Application / Permit
23016-10000-44797
Plan Check / Job No.
B23LA24113
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) DET GARAGE (231 SF) W/ ATT RECROOM (320 SF) TO A (N) 551 SF ADU PER GCS 65852.2(e)(1)(A) AND LAMC 12.22 A.33(c)(d) AND (g) " COMPLY WITH DEPARTMENT ORDER effective date 11/27/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 2/26/2024
Issuing Office
Current Status
CofO Issued on 6/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/22/2023 APPLICANT
Assigned to Plan Check Engineer 12/29/2023 LUISANGEL VALENZUELA
Corrections Issued 12/30/2023 LUISANGEL VALENZUELA
Applicant returned to address corrections 2/5/2024 LUISANGEL VALENZUELA
Plan Check Approved 2/11/2024 LUISANGEL VALENZUELA
Issued 2/26/2024 APPLICANT
CofO in Progress 6/17/2025 JAVIER RAMOS SR
Permit Finaled 6/23/2025 CLAUDIO MORENO
CofO Issued 6/23/2025 CLAUDIO MORENO
Permit Finaled 6/23/2025 CLAUDIO MORENO

Permit Application Clearance Information

Sewer availability Cleared 1/27/2024 ERIK BEASLEY
Address approval Cleared 1/29/2024 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 1/30/2024 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN PARKER, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MICHAEL SERETTI, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
HECTOR RODRIGUEZ, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
BRUCE TODD, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
JAVIER RAMOS SR, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI
MARIAN PODPORA, (213) 978-4508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/28/2024 Partial Approval MICHAEL SERETTI
Pre-Inspection 3/6/2024 Corrections Issued MICHAEL SERETTI
Excavation/Setback/Form/Re-Bar 6/27/2024 Not Ready for Inspection MICHAEL SERETTI
Excavation/Setback/Form/Re-Bar 6/28/2024 Partial Approval MICHAEL SERETTI
Excavation/Setback/Form/Re-Bar 7/9/2024 Approved MICHAEL SERETTI
PLUMBING-Rough 7/18/2024 Partial Approval MICHAEL SERETTI
Sewer 7/18/2024 Approved MICHAEL SERETTI
BUILDING-Rough-Frame 9/13/2024 Approved MICHAEL SERETTI
ELECTRICAL-Rough 9/13/2024 Partial Approval MICHAEL SERETTI
PLUMBING-Rough 9/13/2024 Partial Approval MICHAEL SERETTI
ELECTRICAL-Rough 9/18/2024 Approved JOHN PARKER
Gas Test 9/18/2024 Approved JOHN PARKER
HVAC-Rough 9/18/2024 Approved JOHN PARKER
PLUMBING-Rough 9/18/2024 Approved JOHN PARKER
Insulation 9/23/2024 Approved JOHN PARKER
Shower Pan 9/23/2024 Approved JOHN PARKER
Special/Order Compliance 9/23/2024 Approved JOHN PARKER
ELECTRICAL-Final 11/6/2024 Not Ready for Inspection MICHAEL SERETTI
Service/Power Release 11/6/2024 Approved MICHAEL SERETTI
ELECTRICAL-Final 1/29/2025 Approved MICHAEL SERETTI
Final 1/29/2025 OK to Issue CofO MICHAEL SERETTI
PLUMBING-Final 1/29/2025 Approved MICHAEL SERETTI
SGSOV-Seismic Gas S/O Valve 1/29/2025 SGSOV Approved MICHAEL SERETTI
Smoke Detectors 1/29/2025 Approved MICHAEL SERETTI