8116 S SAN PEDRO ST 90003

Certificate Information: 8116 S SAN PEDRO ST 90003

Application / Permit
23016-10000-44746
Plan Check / Job No.
B23LA24066
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADDITION TO (E) GARAGE AND CONVERT TO ADU PER LAMC 12.22 A.33(c) AND (g)
Permit Issued
Issued on 8/13/2024
Issuing Office
Valley
Current Status
CofO Issued on 5/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2023 APPLICANT
Assigned to Plan Check Engineer 1/18/2024 NGHI SU
Corrections Issued 1/20/2024 NGHI SU
Quality Review Completed 1/24/2024 KEN GILL
Building Plans Picked Up 2/1/2024 APPLICANT
Plan Check Approved 4/12/2024 NGHI SU
Issued 8/13/2024 APPLICANT
CofO in Progress 5/8/2025 MICHAEL LEWIS
Permit Finaled 5/10/2025 DEROLD HAUFF
CofO Issued 5/10/2025 DEROLD HAUFF
Permit Finaled 5/10/2025 DEROLD HAUFF

Permit Application Clearance Information

"Q" conditions Cleared 2/6/2024 JAZMIN ROQUE
Miscellaneous Cleared 2/6/2024 JAZMIN ROQUE
Miscellaneous Cleared 2/6/2024 JAZMIN ROQUE
Roof/Waste drainage to street Cleared 2/6/2024 DAVID LOPEZ
Address approval Cleared 2/8/2024 DAVID LOPEZ
Hydrant and Access approval Cleared 2/24/2024 JOHN CONNEALLY
Eng Process Fee Ord 176,300 Cleared 2/29/2024 JESSICA OPINION
Sewer availability Cleared 2/29/2024 JESSICA OPINION

Contact Information

Contractor Good News Construction Inc; Lic. No.: 967654-B P O BOX 570679      LOS ANGELES, CA 91357
Engineer Dorta,, Michael Rohrs; Lic. No.: C72538 2445 VIA SONOMA      PALOS VERDES ESTATES, CA 90274

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/22/2024 Approved MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 9/9/2024 Not Ready for Inspection MICHAEL LEWIS
Deputy Drilled-In Anchors 9/11/2024 Approved MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 9/12/2024 Approved MICHAEL LEWIS
Footing/Foundation/Slab 9/12/2024 Partial Approval MICHAEL LEWIS
Footing/Foundation/Slab 9/27/2024 Partial Approval MICHAEL LEWIS
ELECTRICAL-Rough 11/7/2024 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 11/7/2024 Approved MICHAEL LEWIS
PLUMBING-Rough 11/7/2024 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Rough 11/12/2024 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 11/12/2024 Approved MICHAEL LEWIS
HVAC-Rough 11/12/2024 Partial Approval MICHAEL LEWIS
PLUMBING-Rough 11/12/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 11/14/2024 Corrections Issued MICHAEL LEWIS
Green Building Rough 11/14/2024 Approved MICHAEL LEWIS
HVAC-Rough 11/14/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 11/18/2024 Approved MICHAEL LEWIS
Insulation 11/18/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 11/18/2024 Approved MICHAEL LEWIS
Drywall Nailing 11/22/2024 Approved ANTHONY RAMOS
Underground Mechanical 12/17/2024 Partial Approval JOHN QUINTANILLA
ELECTRICAL-Final 4/8/2025 Corrections Issued JOHN QUINTANILLA
Final 4/8/2025 Corrections Issued JOHN QUINTANILLA
Green Building Final 4/8/2025 Not Ready for Inspection JOHN QUINTANILLA
HVAC-Final 4/8/2025 Corrections Issued JOHN QUINTANILLA
PLUMBING-Final 4/8/2025 Corrections Issued JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 4/8/2025 SGSOV Not Ready JOHN QUINTANILLA
Smoke Detectors 4/8/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Final 4/23/2025 Approved JOHN QUINTANILLA
Final 4/23/2025 Corrections Issued JOHN QUINTANILLA
Green Building Final 4/23/2025 Approved JOHN QUINTANILLA
HVAC-Final 4/23/2025 Approved JOHN QUINTANILLA
PLUMBING-Final 4/23/2025 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 4/23/2025 SGSOV Not Required JOHN QUINTANILLA
Service/Power Release 4/23/2025 Approved JOHN QUINTANILLA
Final 4/30/2025 Conditional Approval JOHN QUINTANILLA
Final 5/8/2025 OK to Issue CofO MICHAEL LEWIS