1447 S WOOSTER ST 1-8 90035
Certificate Information: 1447 S WOOSTER ST 1-8 90035
- Application / Permit
- 23016-10000-44695
- Plan Check / Job No.
- B23LA24030
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Convert existing garage into accessory dwelling unit per CA Govt. Code 65852.2(e)(1)(A). Work per engineer details. **ePLAN**
- Permit Issued
- Issued on 10/29/2024
- Issuing Office
- Current Status
- CofO Issued on 4/24/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2024 | VICTOR CHEN |
| Corrections Issued | 1/6/2024 | VICTOR CHEN |
| Applicant returned to address corrections | 1/31/2024 | KELVIN CHUONG |
| Applicant returned to address corrections | 2/14/2024 | KELVIN CHUONG |
| Applicant returned to address corrections | 9/18/2024 | KELVIN CHUONG |
| Plan Check Approved | 10/28/2024 | KELVIN CHUONG |
| Issued | 10/29/2024 | APPLICANT |
| CofO in Progress | 3/24/2026 | FARHAD DADBIN |
| Permit Finaled | 4/24/2026 | VASIL MIHALEV |
| CofO Issued | 4/24/2026 | VASIL MIHALEV |
| Permit Finaled | 4/24/2026 | VASIL MIHALEV |
Permit Application Clearance Information
| Address approval | Cleared | 1/19/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 1/19/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2024 | TREVOR QUAN |
| Miscellaneous | Cleared | 2/16/2024 | VICTOR CHEN |
| Tenant Habitability Plan | Cleared | 3/6/2024 | RICARDO BOHORQUEZ |
| "Q" conditions | Cleared | 3/11/2024 | MATHEW QUAN |
| Construction near power lines | Cleared | 9/13/2024 | RIDWAN HARDY |
Contact Information
| Contractor | H Z S Construction; Lic. No.: 1039476-B | , |
| Contractor | H Z S Engineering Inc; Lic. No.: 1039476-B | , |
| Engineer | Shekaramiz,, Hamid; Lic. No.: C82784 | 2 TIMBRE RANCHO SANTA MARGARITA, CA 92688 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/22/2025 | Partial Approval | FARHAD DADBIN |
| Footing/Foundation/Slab | 2/25/2025 | Approved | FARHAD DADBIN |
| Green Building Rough | 3/28/2025 | Approved | FARHAD DADBIN |
| METHANE-Rough | 3/28/2025 | Approved | FARHAD DADBIN |
| Wall Anchors | 3/28/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Wood Frame | 3/28/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Insulation | 5/23/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Insulation | 5/29/2025 | Approved | PAUL DAVIDSON |
| Drywall Nailing | 6/11/2025 | No Access for Inspection | PAUL DAVIDSON |
| Drywall Nailing | 6/12/2025 | Approved | FARHAD DADBIN |
| Interior/Exterior Lathing | 6/24/2025 | Partial Approval | FARHAD DADBIN |
| Interior/Exterior Lathing | 8/4/2025 | Approved | FARHAD DADBIN |
| Final | 10/28/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Green Building Final | 10/28/2025 | Approved | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 10/28/2025 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 10/28/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Wood Frame | 10/28/2025 | Approved | FARHAD DADBIN |
| Final | 11/17/2025 | Not Ready for Inspection | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 11/17/2025 | SGSOV Not Ready | FARHAD DADBIN |
| Smoke Detectors | 11/17/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 3/24/2026 | OK to Issue CofO | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 3/24/2026 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 3/24/2026 | Approved | FARHAD DADBIN |