3749 S HILLCREST DR 90016
Certificate Information: 3749 S HILLCREST DR 90016
- Application / Permit
- 23016-10000-44330
- Plan Check / Job No.
- B23LA23750
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE INTO A (N) 340 SF ADU PER GCS 65852.2. ALL WORK PER ENG.
- Permit Issued
- Issued on 6/3/2024
- Issuing Office
- Current Status
- CofO Issued on 2/2/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2023 | LUISANGEL VALENZUELA |
| Corrections Issued | 12/26/2023 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 1/6/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 1/16/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 5/24/2024 | LUISANGEL VALENZUELA |
| No Progress | 6/3/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 6/3/2024 | LUISANGEL VALENZUELA |
| Issued | 6/3/2024 | APPLICANT |
| CofO in Progress | 1/17/2025 | LUIS CASTRO |
| Permit Finaled | 2/2/2025 | DEROLD HAUFF |
| CofO Issued | 2/2/2025 | DEROLD HAUFF |
| Permit Finaled | 2/2/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/30/2023 | TERRY PHAN |
| Sewer availability | Cleared | 12/30/2023 | TERRY PHAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/2/2024 | TERRY PHAN |
| Construction near power lines | Cleared | 5/22/2024 | TINA MIRANDA |
Contact Information
| Contractor | Green Source Energy Inc; Lic. No.: 1018294-B | , |
| Engineer | Hanna,, Emil Ramzy; Lic. No.: C63602 | 18925 GRANADA CIRCLE NORTHRIDGE, CA 91326 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/1/2024 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 7/3/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 7/3/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 7/9/2024 | Approved | ANTHONY EGSON |
| Footing/Foundation/Slab | 7/9/2024 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 7/9/2024 | Partial Approval | ANTHONY EGSON |
| PLUMBING-Rough | 7/10/2024 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 7/19/2024 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 7/19/2024 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 7/25/2024 | Not Ready for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 7/25/2024 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 8/6/2024 | Corrections Issued | ANTHONY EGSON |
| HVAC-Rough | 8/6/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 8/6/2024 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Rough | 8/6/2024 | Approved | ANTHONY EGSON |
| ELECTRICAL-Rough | 8/8/2024 | Approved | ANTHONY EGSON |
| Green Building Rough | 8/8/2024 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 8/8/2024 | Approved | ANTHONY EGSON |
| Insulation | 8/13/2024 | Approved | ALEX COLIN |
| Sewer | 8/15/2024 | Approved | JOSH MEISTER |
| Underground Mechanical | 8/15/2024 | Partial Approval | JOSH MEISTER |
| BUILDING-Rough-Frame | 8/26/2024 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2024 | Approved | ANTHONY EGSON |
| Shower Pan | 8/26/2024 | Approved | ANTHONY EGSON |
| Drywall Nailing | 8/30/2024 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 8/30/2024 | Approved | ALEX COLIN |
| ELECTRICAL-Final | 10/16/2024 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 10/16/2024 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 10/16/2024 | Approved | ANTHONY EGSON |
| Smoke Detectors | 10/16/2024 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Final | 10/22/2024 | Approved | BARRY HACHE |
| HVAC-Final | 10/22/2024 | Approved | BARRY HACHE |
| PLUMBING-Final | 10/22/2024 | Corrections Issued | BARRY HACHE |
| Final | 11/12/2024 | Not Ready for Inspection | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 11/12/2024 | SGSOV Not Ready | BARRY HACHE |
| Smoke Detectors | 11/12/2024 | No Access for Inspection | BARRY HACHE |
| Final | 11/15/2024 | Corrections Issued | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 11/15/2024 | SGSOV Approved | BARRY HACHE |
| Smoke Detectors | 11/15/2024 | Approved | BARRY HACHE |
| Final | 12/10/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Final | 12/26/2024 | Corrections Issued | LUIS CASTRO |
| Final | 1/16/2025 | OK to Issue CofO | LUIS CASTRO |