23349-23351 S HALLDALE AVE 90710
Certificate Information: 23349-23351 S HALLDALE AVE 90710
- Application / Permit
- 23016-10000-44319
- Plan Check / Job No.
- B23LA23739
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT EXISTING 20'-4" X 20'-0" ATTACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) - PER ENGINEER
- Permit Issued
- Issued on 2/15/2024
- Issuing Office
- Current Status
- CofO Issued on 3/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2023 | DANIEL ABRAMYAN |
| Corrections Issued | 12/21/2023 | DANIEL ABRAMYAN |
| Plan Check Approved | 2/8/2024 | DANIEL ABRAMYAN |
| Issued | 2/15/2024 | APPLICANT |
| CofO in Progress | 3/12/2025 | EUGENE CASSIDY |
| Permit Finaled | 3/14/2025 | ANSON MAGLASANG |
| CofO Issued | 3/14/2025 | ANSON MAGLASANG |
| Permit Finaled | 3/14/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 1/2/2024 | KHAING AYE |
| Eng Process Fee Ord 176,300 | Cleared | 1/8/2024 | KHAING AYE |
| Sewer availability | Cleared | 1/16/2024 | KHAING AYE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gerges,, Atef; Lic. No.: NA94252 | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/9/2024 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 9/9/2024 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 10/23/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Rough | 10/23/2024 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 10/23/2024 | Partial Approval | EUGENE CASSIDY |
| METHANE-Rough | 10/23/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 10/23/2024 | Partial Approval | EUGENE CASSIDY |
| Shower Pan | 10/23/2024 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 11/13/2024 | Approved | BEN MOLSTAD |
| HVAC-Rough | 11/13/2024 | Approved | BEN MOLSTAD |
| Insulation | 11/13/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 11/13/2024 | Approved | BEN MOLSTAD |
| Drywall Nailing | 11/18/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 11/18/2024 | Approved | BEN MOLSTAD |
| Final | 2/11/2025 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 2/11/2025 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 2/11/2025 | Approved | EUGENE CASSIDY |
| Final | 2/20/2025 | Corrections Issued | EUGENE CASSIDY |
| Final | 3/6/2025 | Corrections Issued | EUGENE CASSIDY |
| Service/Power Release | 3/6/2025 | Not Required | EUGENE CASSIDY |
| ELECTRICAL-Final | 3/11/2025 | Approved | EUGENE CASSIDY |
| Final | 3/11/2025 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 3/11/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 3/11/2025 | Approved | EUGENE CASSIDY |