23349-23351 S HALLDALE AVE 90710

Certificate Information: 23349-23351 S HALLDALE AVE 90710

Application / Permit
23016-10000-44319
Plan Check / Job No.
B23LA23739
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EXISTING 20'-4" X 20'-0" ATTACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A) - PER ENGINEER
Permit Issued
Issued on 2/15/2024
Issuing Office
Current Status
CofO Issued on 3/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/18/2023 APPLICANT
Assigned to Plan Check Engineer 12/20/2023 DANIEL ABRAMYAN
Corrections Issued 12/21/2023 DANIEL ABRAMYAN
Plan Check Approved 2/8/2024 DANIEL ABRAMYAN
Issued 2/15/2024 APPLICANT
CofO in Progress 3/12/2025 EUGENE CASSIDY
Permit Finaled 3/14/2025 ANSON MAGLASANG
CofO Issued 3/14/2025 ANSON MAGLASANG
Permit Finaled 3/14/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 1/2/2024 KHAING AYE
Eng Process Fee Ord 176,300 Cleared 1/8/2024 KHAING AYE
Sewer availability Cleared 1/16/2024 KHAING AYE

Contact Information

Contractor Owner-Builder       ,
Engineer Gerges,, Atef; Lic. No.: NA94252       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/9/2024 Approved JOSEPH MCGARRY
PLUMBING-Rough 9/9/2024 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 10/23/2024 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 10/23/2024 Approved EUGENE CASSIDY
Interior/Exterior Lathing 10/23/2024 Partial Approval EUGENE CASSIDY
METHANE-Rough 10/23/2024 Approved EUGENE CASSIDY
PLUMBING-Rough 10/23/2024 Partial Approval EUGENE CASSIDY
Shower Pan 10/23/2024 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 11/13/2024 Approved BEN MOLSTAD
HVAC-Rough 11/13/2024 Approved BEN MOLSTAD
Insulation 11/13/2024 Approved BEN MOLSTAD
PLUMBING-Rough 11/13/2024 Approved BEN MOLSTAD
Drywall Nailing 11/18/2024 Approved BEN MOLSTAD
Interior/Exterior Lathing 11/18/2024 Approved BEN MOLSTAD
Final 2/11/2025 Corrections Issued EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 2/11/2025 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 2/11/2025 Approved EUGENE CASSIDY
Final 2/20/2025 Corrections Issued EUGENE CASSIDY
Final 3/6/2025 Corrections Issued EUGENE CASSIDY
Service/Power Release 3/6/2025 Not Required EUGENE CASSIDY
ELECTRICAL-Final 3/11/2025 Approved EUGENE CASSIDY
Final 3/11/2025 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 3/11/2025 Approved EUGENE CASSIDY
PLUMBING-Final 3/11/2025 Approved EUGENE CASSIDY