7050 S 6TH AVE 1-10 90043

Certificate Information: 7050 S 6TH AVE 1-10 90043

Application / Permit
23016-10000-44181
Plan Check / Job No.
B23LA23658
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: Conversion of (E) carport to two ADU's.
Permit Issued
Issued on 10/11/2024
Issuing Office
Current Status
CofO Issued on 3/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2023 APPLICANT
Assigned to Plan Check Engineer 1/11/2024 ARSALAN SHABESTARI
Assigned to Zoning Architect 1/11/2024 ARSALAN SHABESTARI
Corrections Issued 1/25/2024 ARSALAN SHABESTARI
Quality Review Completed 2/6/2024 GARO TELMI
Applicant returned to address corrections 7/24/2024 ARSALAN SHABESTARI
Plan Check Approved 10/7/2024 ARSALAN SHABESTARI
Issued 10/11/2024 APPLICANT
CofO in Progress 3/6/2025 ERNESTO CORRAL
Permit Finaled 3/6/2025 ERNESTO CORRAL
CofO Issued 3/6/2025 ERNESTO CORRAL
Permit Finaled 3/6/2025 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 3/21/2024 CHRISTINA BRACO
Sewer availability Cleared 3/21/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 3/22/2024 CHRISTINA BRACO
Community Plan Implem. Overlay Cleared 6/6/2024 ISAIAH ROSS
ZA Case Cleared 6/12/2024 DANIEL CORONADO
Historic Resource Verification Cleared 6/13/2024 ELIZABETH GALLARDO
Redevelopment Project Area Cleared 6/13/2024 ELIZABETH GALLARDO
Green Code Cleared 6/18/2024 Gurunath Nesarajah
DAS Clearance Cleared 7/17/2024 ELIZABETH TOMS
Zoning Plan Check Cleared 10/7/2024 Gurunath Nesarajah

Contact Information

Contractor Line Electric Inc; Lic. No.: 910172-B       ,

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/16/2024 Approved DARRYL ARNOLD
Footing/Foundation/Slab 11/21/2024 Approved DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 12/3/2024 Conditional Approval DARRYL ARNOLD
Final 12/4/2024 Not Ready for Inspection DARRYL ARNOLD
Green Building Final 12/4/2024 Conditional Approval DARRYL ARNOLD
Green Building Rough 12/4/2024 Conditional Approval DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 12/4/2024 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 12/4/2024 Corrections Issued DARRYL ARNOLD
Wood Frame 12/4/2024 Conditional Approval DARRYL ARNOLD
Green Building Rough 12/9/2024 Approved DARRYL ARNOLD
Wood Frame 12/9/2024 Not Ready for Inspection DARRYL ARNOLD
Insulation 12/10/2024 Approved ALFREDO LOPEZ
Drywall Nailing 12/16/2024 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 12/16/2024 Conditional Approval DARRYL ARNOLD
Final 2/26/2025 Not Ready for Inspection DARRYL ARNOLD
Green Building Final 2/26/2025 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 2/26/2025 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 2/26/2025 Not Ready for Inspection DARRYL ARNOLD
Wood Frame 2/26/2025 Corrections Issued DARRYL ARNOLD
Final 3/6/2025 OK to Issue CofO ERNESTO CORRAL
Green Building Final 3/6/2025 Approved ERNESTO CORRAL
SGSOV-Seismic Gas S/O Valve 3/6/2025 SGSOV Approved ERNESTO CORRAL
Smoke Detectors 3/6/2025 Approved ERNESTO CORRAL
Wood Frame 3/6/2025 Approved ERNESTO CORRAL