12421-12423 W TEXAS AVE 90025

Certificate Information: 12421-12423 W TEXAS AVE 90025

Application / Permit
23016-10000-43737
Plan Check / Job No.
B23LA23401
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Convert parking and laundry space to 2 separate ADU units
Permit Issued
Issued on 2/19/2025
Issuing Office
Current Status
CofO Issued on 7/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2023 APPLICANT
Assigned to Zoning Architect 1/4/2024 JOE VO
Assigned to Plan Check Engineer 1/4/2024 JOE VO
Corrections Issued 1/10/2024 JOE VO
Quality Review Completed 1/11/2024 PRANITA SHAH
Applicant returned to address corrections 3/27/2024 JOE VO
Applicant returned to address corrections 8/20/2024 JOE VO
Plan Check Approved 10/4/2024 JOE VO
No Progress 2/5/2025 JOE VO
Plan Check Approved 2/12/2025 JOE VO
Issued 2/19/2025 APPLICANT
CofO in Progress 7/10/2026 PAUL DAVIDSON
No Progress 7/14/2026 PAUL DAVIDSON
CofO in Progress 7/14/2026 PAUL DAVIDSON
Permit Finaled 7/23/2026 TED RIES
CofO Issued 7/23/2026 TED RIES
Permit Finaled 7/23/2026 TED RIES

Permit Application Clearance Information

Address approval Cleared 1/12/2024 DINAH GARIN
Sewer availability Cleared 1/12/2024 DINAH GARIN
"Q" conditions Cleared 1/16/2024 DALIA MOKAYED
DAS Clearance Cleared 1/16/2024 JOE VO
Eng Process Fee Ord 176,300 Cleared 1/17/2024 DINAH GARIN
Zoning Plan Check Cleared 3/26/2024 JOE VO
Hydrant and Access approval Cleared 4/25/2024 RUEL COLE
Green Code Cleared 7/23/2024 AARON COSTA
Specific Plan Cleared 1/28/2025 MOHAMMAD HASAN

Contact Information

Contractor Helio Group; Lic. No.: 1004478-B       ,
Contractor Helio; Lic. No.: 1004478-B       ,
Engineer Willoughby,, David; Lic. No.: S7161 624 N 420 W      MAPLETON, UT 84664

Inspector Information

CASIMIR BRITTON, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI
SHAVONNE ESPINOZA, (310) 914-3913 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Interior/Exterior Lathing 7/9/2025 Partial Approval CASIMIR BRITTON
Green Building Rough 10/24/2025 Not Ready for Inspection CASIMIR BRITTON
Insulation 10/24/2025 Not Ready for Inspection CASIMIR BRITTON
Wood Frame 10/24/2025 Corrections Issued CASIMIR BRITTON
Green Building Rough 11/24/2025 Not Ready for Inspection CASIMIR BRITTON
Insulation 11/24/2025 Conditional Approval CASIMIR BRITTON
Wood Frame 11/24/2025 Not Ready for Inspection CASIMIR BRITTON
Insulation 11/26/2025 Partial Approval CASIMIR BRITTON
Drywall Nailing 12/3/2025 Partial Approval FARHAD DADBIN
Final 4/8/2026 Not Ready for Inspection CASIMIR BRITTON
Green Building Final 4/8/2026 Approved CASIMIR BRITTON
Green Building Rough 4/8/2026 Approved CASIMIR BRITTON
SGSOV-Seismic Gas S/O Valve 4/8/2026 SGSOV Not Ready CASIMIR BRITTON
Smoke Detectors 4/8/2026 Not Ready for Inspection CASIMIR BRITTON
Wood Frame 4/8/2026 Approved CASIMIR BRITTON
Final 7/8/2026 OK to Issue CofO PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 7/8/2026 SGSOV Approved PAUL DAVIDSON
Smoke Detectors 7/8/2026 Approved PAUL DAVIDSON