5160 S WILTON PL 90062

Certificate Information: 5160 S WILTON PL 90062

Application / Permit
23016-10000-43716
Plan Check / Job No.
B23LA23388
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 2ND STORY STORAGE ROOM INTO AN ADU ABOVE (E) GARAGE.
Permit Issued
Issued on 6/3/2024
Issuing Office
Metro
Current Status
CofO Issued on 12/12/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2023 APPLICANT
Assigned to Plan Check Engineer 12/14/2023 SAMUEL GONZALEZ
Corrections Issued 12/16/2023 SAMUEL GONZALEZ
Building Plans Picked Up 12/20/2023 APPLICANT
Plan Check Approved 5/10/2024 JOHN MESIAS
Issued 6/3/2024 APPLICANT
CofO in Progress 12/11/2024 SABAS ALONSO
Permit Finaled 12/12/2024 DEROLD HAUFF
CofO Issued 12/12/2024 DEROLD HAUFF
Permit Finaled 12/12/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/30/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 4/30/2024 JUSTIN BICOL
Sewer availability Cleared 4/30/2024 JUSTIN BICOL
Construction near power lines Cleared 5/1/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/24/2024 Corrections Issued SABAS ALONSO
ELECTRICAL-Rough 8/1/2024 Approved SABAS ALONSO
Footing/Foundation/Slab 8/1/2024 Approved SABAS ALONSO
Green Building Rough 8/1/2024 Not Ready for Inspection SABAS ALONSO
PLUMBING-Rough 8/1/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 8/6/2024 Partial Approval ALEX COLIN
HVAC-Rough 8/8/2024 Approved JOSH MEISTER
Underground Mechanical 8/8/2024 Partial Approval JOSH MEISTER
BUILDING-Rough-Frame 8/12/2024 Corrections Issued MICHAEL LEWIS
Green Building Rough 8/12/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 8/20/2024 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 8/21/2024 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 8/23/2024 Approved SABAS ALONSO
Insulation 8/23/2024 Corrections Issued SABAS ALONSO
Drywall Nailing 8/28/2024 Approved CRAIG DAVIS
Insulation 8/28/2024 Corrections Issued CRAIG DAVIS
BUILDING-Rough-Frame 9/12/2024 Approved SABAS ALONSO
ELECTRICAL-Final 9/12/2024 Corrections Issued SABAS ALONSO
Insulation 9/12/2024 Approved SABAS ALONSO
Interior/Exterior Lathing 9/12/2024 Approved SABAS ALONSO
Service/Power Release 9/12/2024 Not Ready for Inspection SABAS ALONSO
Final 11/5/2024 Corrections Issued SABAS ALONSO
Green Building Final 11/5/2024 Corrections Issued SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 11/5/2024 SGSOV Approved SABAS ALONSO
Smoke Detectors 11/5/2024 Approved SABAS ALONSO
Final 12/9/2024 Corrections Issued SABAS ALONSO
Green Building Final 12/9/2024 Approved SABAS ALONSO
Final 12/10/2024 OK to Issue CofO SABAS ALONSO