5160 S WILTON PL 90062
Certificate Information: 5160 S WILTON PL 90062
- Application / Permit
- 23016-10000-43716
- Plan Check / Job No.
- B23LA23388
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) 2ND STORY STORAGE ROOM INTO AN ADU ABOVE (E) GARAGE.
- Permit Issued
- Issued on 6/3/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/14/2023 | SAMUEL GONZALEZ |
| Corrections Issued | 12/16/2023 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 12/20/2023 | APPLICANT |
| Plan Check Approved | 5/10/2024 | JOHN MESIAS |
| Issued | 6/3/2024 | APPLICANT |
| CofO in Progress | 12/11/2024 | SABAS ALONSO |
| Permit Finaled | 12/12/2024 | DEROLD HAUFF |
| CofO Issued | 12/12/2024 | DEROLD HAUFF |
| Permit Finaled | 12/12/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/30/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 4/30/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 4/30/2024 | JUSTIN BICOL |
| Construction near power lines | Cleared | 5/1/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/24/2024 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 8/1/2024 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 8/1/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 8/1/2024 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 8/1/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 8/6/2024 | Partial Approval | ALEX COLIN |
| HVAC-Rough | 8/8/2024 | Approved | JOSH MEISTER |
| Underground Mechanical | 8/8/2024 | Partial Approval | JOSH MEISTER |
| BUILDING-Rough-Frame | 8/12/2024 | Corrections Issued | MICHAEL LEWIS |
| Green Building Rough | 8/12/2024 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 8/20/2024 | Corrections Issued | CRAIG DAVIS |
| BUILDING-Rough-Frame | 8/21/2024 | Corrections Issued | CRAIG DAVIS |
| BUILDING-Rough-Frame | 8/23/2024 | Approved | SABAS ALONSO |
| Insulation | 8/23/2024 | Corrections Issued | SABAS ALONSO |
| Drywall Nailing | 8/28/2024 | Approved | CRAIG DAVIS |
| Insulation | 8/28/2024 | Corrections Issued | CRAIG DAVIS |
| BUILDING-Rough-Frame | 9/12/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 9/12/2024 | Corrections Issued | SABAS ALONSO |
| Insulation | 9/12/2024 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 9/12/2024 | Approved | SABAS ALONSO |
| Service/Power Release | 9/12/2024 | Not Ready for Inspection | SABAS ALONSO |
| Final | 11/5/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 11/5/2024 | Corrections Issued | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/5/2024 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 11/5/2024 | Approved | SABAS ALONSO |
| Final | 12/9/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 12/9/2024 | Approved | SABAS ALONSO |
| Final | 12/10/2024 | OK to Issue CofO | SABAS ALONSO |