947-949 1/2 W 76TH ST 90044

Certificate Information: 947-949 1/2 W 76TH ST 90044

Application / Permit
23016-10000-43498
Plan Check / Job No.
B23LA23280
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
EPLAN: CONVERT (E) 2 ATTACHED GARAGE AND LAUNDRY AREA BELOW DUPLEX INTO 2 NEW IRREGULAR SHAPED ACCESSORY DWELLING UNITS TO COMPLY WITH LAMC 12.22 A.33(c) AND (e) PER ENGINEERING
Permit Issued
Issued on 3/5/2024
Issuing Office
Current Status
CofO Issued on 7/24/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2023 APPLICANT
Assigned to Plan Check Engineer 12/15/2023 ALFRED RAMIREZ
Corrections Issued 12/16/2023 ALFRED RAMIREZ
Plan Check Approved 2/1/2024 ALFRED RAMIREZ
Issued 3/5/2024 APPLICANT
CofO in Progress 7/16/2024 MICHAEL LEWIS
Permit Finaled 7/24/2024 DEROLD HAUFF
CofO Issued 7/24/2024 DEROLD HAUFF
Permit Finaled 7/24/2024 DEROLD HAUFF

Permit Application Clearance Information

Historic Resource Verification Cleared 12/29/2023 RAFAEL FONTES
Address approval Cleared 1/6/2024 ADRIAN SANCHEZ
Sewer availability Cleared 1/6/2024 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 1/10/2024 ADRIAN SANCHEZ
Redevelopment Project Area Cleared 1/19/2024 ELIZABETH GALLARDO
ZI Cleared 1/19/2024 ELIZABETH GALLARDO

Contact Information

Contractor Owner-Builder       ,
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/4/2024 Approved MICHAEL LEWIS
Underground Mechanical 4/4/2024 Approved MICHAEL LEWIS
Deputy Drilled-In Anchors 4/26/2024 Conditional Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 4/26/2024 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/1/2024 Partial Approval MICHAEL LEWIS
Gas Test 5/1/2024 Approved MICHAEL LEWIS
Rough-Elec/Plmb/HVAC 5/1/2024 Corrections Issued MICHAEL LEWIS
BUILDING-Rough-Frame 5/7/2024 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Rough 5/7/2024 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 5/7/2024 Approved MICHAEL LEWIS
Green Building Rough 5/7/2024 Not Ready for Inspection MICHAEL LEWIS
HVAC-Rough 5/7/2024 Approved MICHAEL LEWIS
Insulation 5/7/2024 Partial Approval MICHAEL LEWIS
PLUMBING-Rough 5/7/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 5/9/2024 Approved MICHAEL LEWIS
Green Building Rough 5/15/2024 Approved MICHAEL LEWIS
Insulation 5/15/2024 Approved MICHAEL LEWIS
Drywall Nailing 5/23/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 5/23/2024 Approved MICHAEL LEWIS
Service/Power Release 7/3/2024 Not Ready for Inspection MICHAEL LEWIS
Final 7/11/2024 Corrections Issued MICHAEL LEWIS
Gas Test 7/11/2024 Approved MICHAEL LEWIS
Green Building Final 7/11/2024 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 7/11/2024 SGSOV Approved MICHAEL LEWIS
Service/Power Release 7/11/2024 Not Ready for Inspection MICHAEL LEWIS
Smoke Detectors 7/11/2024 Approved MICHAEL LEWIS
Final 7/15/2024 OK to Issue CofO MICHAEL LEWIS
Service/Power Release 7/15/2024 Approved MICHAEL LEWIS