638 1/2 W 107TH ST 90044

Certificate Information: 638 1/2 W 107TH ST 90044

Application / Permit
23016-10000-43330
Plan Check / Job No.
B23LA23179
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) DETACHED GARAGE INTO A (N) 316 SF ACCESSORY DWELLING UNIT TO COMPLY WITH CA Govt. Code 65852.2(e)(1)(A), ALL WORK PER ENG.
Permit Issued
Issued on 3/1/2024
Issuing Office
Current Status
CofO Issued on 2/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/11/2023 APPLICANT
Assigned to Plan Check Engineer 12/14/2023 MICHAEL LOPEZ
Corrections Issued 12/14/2023 MICHAEL LOPEZ
Applicant returned to address corrections 2/5/2024 ALFRED RAMIREZ
Applicant returned to address corrections 2/20/2024 LUISANGEL VALENZUELA
Plan Check Approved 2/29/2024 LUISANGEL VALENZUELA
Issued 3/1/2024 APPLICANT
CofO in Progress 2/20/2026 JOSEPH MCGARRY
Permit Finaled 2/20/2026 ANSON MAGLASANG
Permit Finaled 2/20/2026 ANSON MAGLASANG
CofO Issued 2/20/2026 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 1/16/2024 ANTHONY TRAN
Sewer availability Cleared 1/16/2024 ANTHONY TRAN
Eng Process Fee Ord 176,300 Cleared 2/2/2024 ANTHONY TRAN

Contact Information

Contractor Owner-Builder       ,
Engineer Crook,, Barrett Cameron; Lic. No.: C57196 5306 MULHOLLAND DRIVE      SUMMERVILLE, SC 29485

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/20/2024 Not Ready for Inspection JAMES CHAVEZ
Pre-Inspection 6/20/2024 Partial Inspection JAMES CHAVEZ
Deputy Drilled-In Anchors 1/28/2025 No Access for Inspection BEN MOLSTAD
Footing/Foundation/Slab 2/3/2025 Approved BEN MOLSTAD
Green Building Rough 2/14/2025 Not Ready for Inspection BEN MOLSTAD
Wood Frame 2/14/2025 Not Ready for Inspection BEN MOLSTAD
Final 1/15/2026 Corrections Issued BEN MOLSTAD
Green Building Final 1/15/2026 Not Ready for Inspection BEN MOLSTAD
Green Building Rough 1/15/2026 Approved BEN MOLSTAD
SGSOV-Seismic Gas S/O Valve 1/15/2026 SGSOV Approved BEN MOLSTAD
Smoke Detectors 1/15/2026 Approved BEN MOLSTAD
Wood Frame 1/15/2026 Approved BEN MOLSTAD
Final 2/17/2026 OK to Issue CofO JOSEPH MCGARRY
Green Building Final 2/17/2026 Approved JOSEPH MCGARRY