2922 S CRENSHAW BLVD 3RD FLR 90016
Certificate Information: 2922 S CRENSHAW BLVD 3RD FLR 90016
- Application / Permit
- 23016-10000-43222
- Plan Check / Job No.
- B23LA23106
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- TENANT IMPROVEMENT ON APPROX 18,751 SQ FT, INCLUDING NEW NON STRUCTURAL WALL, LIGHTING DESIGN LAYOUT AND FINISHES. NEW FIRE RATED CORRIDOR AND NEW RESTROOMS.
- Permit Issued
- Issued on 1/29/2024
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 11/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/7/2023 | ZAW HAN |
| Corrections Issued | 12/7/2023 | ZAW HAN |
| Plan Check Approved | 1/22/2024 | MINA HABILI |
| Issued | 1/29/2024 | APPLICANT |
| Permit Finaled | 11/5/2024 | JAMES POWERS |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 1/17/2024 | LAMBERT GIESSINGER |
| Redevelopment Project Area | Cleared | 1/18/2024 | ELIZABETH GALLARDO |
Contact Information
| Architect | Algaze,, Nelson; Lic. No.: C21090 | 1524 1ST STREET MANHATTAN BEACH, CA 90266 |
| Contractor | Owner-Builder | , |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 4/23/2024 | Approved | DARRYL ARNOLD |
| Light Gage Steel Frame | 6/17/2024 | Partial Approval | ALFREDO LOPEZ |
| Insulation | 6/28/2024 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 7/9/2024 | Partial Approval | ALFREDO LOPEZ |
| Insulation | 8/8/2024 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 8/14/2024 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 8/29/2024 | Partial Approval | ALFREDO LOPEZ |
| T-Bar Ceiling | 9/9/2024 | Partial Approval | ALFREDO LOPEZ |
| Pre-Inspection | 10/30/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Pre-Inspection | 10/31/2024 | Partial Approval | JAMES POWERS |
| Final | 11/5/2024 | Permit Finaled | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 11/5/2024 | SGSOV No Gas | JAMES POWERS |
| Smoke Detectors | 11/5/2024 | Approved | JAMES POWERS |