114 N KILKEA DR 90048
Certificate Information: 114 N KILKEA DR 90048
- Application / Permit
- 23016-10000-43154
- Plan Check / Job No.
- B23LA23062
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERT EXISTING 369 SQ. FT. GARAGE TO ADU PER STATE LAW ***13D SPRINKLER REQUIRED***
- Permit Issued
- Issued on 5/1/2024
- Issuing Office
- Current Status
- Issued on 5/1/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/18/2023 | KHUONG TRUONG |
| Corrections Issued | 12/19/2023 | KHUONG TRUONG |
| Plan Check Approved | 4/17/2024 | KHUONG TRUONG |
| Issued | 5/1/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/9/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 1/9/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2024 | DAVID LOPEZ |
| Construction near power lines | Cleared | 4/8/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 4/8/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Mehran Mehrdad; Lic. No.: 1100112-B | , |
| Engineer | Terrio,, Greyson Franklin; Lic. No.: NA87383 | , |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/28/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Underground Mechanical | 6/28/2024 | Corrections Issued | MEL KHACHATOURIAN |
| PLUMBING-Rough | 7/2/2024 | Partial Approval | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 7/17/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 7/30/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Underground Mechanical | 7/30/2024 | Partial Approval | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 8/30/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 9/4/2024 | Partial Approval | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 9/9/2024 | Approved | SEAN HAUPT |
| Excavation/Setback/Form/Re-Bar | 9/27/2024 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 9/27/2024 | Approved | SEAN HAUPT |
| BUILDING-Rough-Frame | 10/29/2024 | Corrections Issued | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 10/29/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Rough | 10/29/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| METHANE-Rough | 10/29/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 10/29/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 11/15/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 11/15/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| Green Building Rough | 11/15/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| PLUMBING-Rough | 11/15/2024 | No Access for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 11/19/2024 | Corrections Issued | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 11/19/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Green Building Rough | 11/19/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Rough | 11/19/2024 | Approved | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2024 | Approved | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2024 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 1/14/2025 | Approved | MEL KHACHATOURIAN |
| Insulation | 1/14/2025 | Approved | MEL KHACHATOURIAN |
| Drywall Nailing | 1/17/2025 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 1/29/2025 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 1/29/2025 | Approved | MEL KHACHATOURIAN |