2137 S SELBY AVE 90025

Certificate Information: 2137 S SELBY AVE 90025

Application / Permit
23016-10000-43120
Plan Check / Job No.
B23LA23026
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: Convert existing 2nd floor Rec room to accessory dwelling unit 675sqft per state law (no structural changes)
Permit Issued
Issued on 4/16/2024
Issuing Office
Current Status
CofO Issued on 9/7/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2023 APPLICANT
Assigned to Plan Check Engineer 12/13/2023 KHUONG TRUONG
Corrections Issued 12/13/2023 KHUONG TRUONG
Plan Check Approved 3/27/2024 DANIEL SANJUAN
Issued 4/16/2024 APPLICANT
CofO in Progress 8/24/2024 MICHAEL PELHAM
Permit Finaled 9/7/2024 RICHARD STEINBACH
Permit Finaled 9/7/2024 RICHARD STEINBACH
CofO Issued 9/7/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 1/17/2024 LIAM ODONOVAN
Sewer availability Cleared 1/17/2024 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 1/23/2024 LIAM ODONOVAN
Specific Plan Cleared 1/23/2024 FREDDY GARCIA
Construction near power lines Cleared 3/5/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/3/2024 Approved ASHLEY THOMPSON
PLUMBING-Final 5/14/2024 Not Ready for Inspection SEAN HAUPT
Pre-Inspection 5/14/2024 Partial Approval SEAN HAUPT
BUILDING-Rough-Frame 5/24/2024 Partial Approval KIRK SANDERS
METHANE-Rough 5/24/2024 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 6/7/2024 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 6/7/2024 Corrections Issued KIRK SANDERS
HVAC-Rough 6/7/2024 Corrections Issued KIRK SANDERS
METHANE-Rough 6/7/2024 Not Ready for Inspection KIRK SANDERS
PLUMBING-Rough 6/7/2024 Corrections Issued KIRK SANDERS
Rough-Elec/Plmb/HVAC 6/7/2024 Not Ready for Inspection KIRK SANDERS
ELECTRICAL-Rough 7/8/2024 Partial Approval KIRK SANDERS
HVAC-Rough 7/8/2024 Approved KIRK SANDERS
METHANE-Rough 7/8/2024 Not Ready for Inspection KIRK SANDERS
PLUMBING-Rough 7/8/2024 Partial Approval KIRK SANDERS
PLUMBING-Rough 7/17/2024 Approved KIRK SANDERS
Rough-Elec/Plmb/HVAC 7/17/2024 Partial Approval KIRK SANDERS
BUILDING-Rough-Frame 7/22/2024 Approved KIRK SANDERS
Drywall Nailing 7/22/2024 Approved KIRK SANDERS
METHANE-Rough 7/22/2024 Approved KIRK SANDERS
Final 7/29/2024 Corrections Issued KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 7/29/2024 SGSOV Not Ready KIRK SANDERS
Smoke Detectors 7/29/2024 Approved KIRK SANDERS
Final 8/8/2024 OK to Issue CofO KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 8/8/2024 SGSOV Approved KIRK SANDERS