1850 W SLAUSON AVE 90047
Certificate Information: 1850 W SLAUSON AVE 90047
- Application / Permit
- 23016-10000-42894
- Plan Check / Job No.
- B23LA22905
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Coffee Shop
- Work Description
- EPLAN Remodel to an existing Starbucks Coffee Tenant Improvement. Scope is Limited to Replacement and/or Repair of existing Casework: Minor Equipment Changes, new interior partition, modified lighting, reconfiguration of floor sinks to match casework/equipment changes, and revised electrical panel schedule to match equipment
- Permit Issued
- Issued on 5/7/2024
- Issuing Office
- Current Status
- Permit Finaled on 1/3/2025
Permit Application Status History
| Submitted | 12/5/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/8/2023 | PINANK PATEL |
| Corrections Issued | 12/12/2023 | PINANK PATEL |
| Plan Check Approved | 3/21/2024 | PINANK PATEL |
| Issued | 5/7/2024 | APPLICANT |
| Permit Finaled | 1/3/2025 | ALFREDO LOPEZ |
Permit Application Clearance Information
| Redevelopment Project Area | Cleared | 1/30/2024 | ELIZABETH GALLARDO |
| ZI | Cleared | 1/30/2024 | ELIZABETH GALLARDO |
| ZI | Cleared | 3/15/2024 | MANERI ROMAN |
| ZI | Cleared | 3/20/2024 | DAVID URITA |
Contact Information
| Architect | Winkler,, Page; Lic. No.: C31839 | , |
| Contractor | Excel Construction Services Inc; Lic. No.: 852879-B | , |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/15/2024 | Conditional Approval | DARRYL ARNOLD |
| Light Gage Steel Frame | 7/15/2024 | Conditional Approval | DARRYL ARNOLD |
| Drywall Nailing | 7/17/2024 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 7/17/2024 | Approved | DARRYL ARNOLD |
| T-Bar Ceiling | 7/17/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| Drywall Nailing | 7/19/2024 | Conditional Approval | DARRYL ARNOLD |
| T-Bar Ceiling | 7/19/2024 | Conditional Approval | DARRYL ARNOLD |
| Final | 7/30/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 7/30/2024 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 7/30/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 7/31/2024 | Partial Inspection | ALFREDO LOPEZ |
| Final | 1/3/2025 | Permit Finaled | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 1/3/2025 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 1/3/2025 | Approved | ALFREDO LOPEZ |