8055 S DUNBARTON AVE 90045
Certificate Information: 8055 S DUNBARTON AVE 90045
- Application / Permit
- 23016-10000-42426
- Plan Check / Job No.
- B23LA22734
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan GARAGE CONVERSION INTO A.D.U. (363 SQ. FT.) PER CA Govt. Code 65852.2(e)(1)(A)
- Permit Issued
- Issued on 1/23/2024
- Issuing Office
- Current Status
- CofO Issued on 8/13/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/3/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/6/2023 | ALFREDO JARA |
| Corrections Issued | 12/6/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 1/12/2024 | ALFREDO JARA |
| Plan Check Approved | 1/16/2024 | ALFREDO JARA |
| Issued | 1/23/2024 | APPLICANT |
| CofO in Progress | 8/7/2024 | BOBBY KEY |
| Permit Finaled | 8/13/2024 | RICHARD STEINBACH |
| CofO Issued | 8/13/2024 | RICHARD STEINBACH |
| Permit Finaled | 8/13/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 12/12/2023 | VLADIMIR ARUTYUNYAN |
| Roof/Waste drainage to street | Cleared | 12/12/2023 | VLADIMIR ARUTYUNYAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/14/2023 | VLADIMIR ARUTYUNYAN |
| Sewer availability | Cleared | 12/14/2023 | VLADIMIR ARUTYUNYAN |
| Specific Plan | Cleared | 1/10/2024 | ALESSANDRO MERCURI |
Contact Information
| Contractor | A P Remodeling Inc; Lic. No.: 1049032-B | , |
| Contractor | Ap Remodeling Inc; Lic. No.: 1049032-B | , |
| Engineer | Dominguez,, Refugio; Lic. No.: C50820 | 254 COTTONWOOD ST ONTARIO, CA 91761 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/27/2024 | Approved | BOBBY KEY |
| Sewer | 3/27/2024 | Partial Approval | BOBBY KEY |
| Sewer | 4/1/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Rough | 4/29/2024 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Rough | 4/29/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 4/29/2024 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2024 | Not Ready for Inspection | BOBBY KEY |
| HVAC-Rough | 5/7/2024 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 5/9/2024 | Not Ready for Inspection | BOBBY KEY |
| BUILDING-Rough-Frame | 5/15/2024 | Approved | RICHARD STEINBACH |
| Green Building Rough | 5/15/2024 | Approved | RICHARD STEINBACH |
| Interior/Exterior Lathing | 5/15/2024 | Partial Approval | RICHARD STEINBACH |
| Insulation | 5/22/2024 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 5/22/2024 | Approved | TEMISTOCLES CAAL |
| Shower Pan | 5/22/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 5/28/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 7/2/2024 | Corrections Issued | BOBBY KEY |
| Final | 7/2/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 7/2/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 7/2/2024 | Approved | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 7/2/2024 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 7/2/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 8/7/2024 | Approved | BOBBY KEY |
| Final | 8/7/2024 | OK to Issue CofO | BOBBY KEY |
| HVAC-Final | 8/7/2024 | Approved | BOBBY KEY |
| PLUMBING-Final | 8/7/2024 | Approved | BOBBY KEY |
| Special/Order Compliance | 8/7/2024 | Partial Inspection | TEMISTOCLES CAAL |