6767 W HOLLYWOOD BLVD 90028

Certificate Information: 6767 W HOLLYWOOD BLVD 90028

Application / Permit
23016-10000-42417
Plan Check / Job No.
B23LA22728
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(4) Museum for profit
Work Description
ePlan PROPOSED CHANGE OF USE FROM RETAIL TO THEATER.
Permit Issued
Issued on 7/30/2024
Issuing Office
Current Status
CofO Issued on 3/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2023 APPLICANT
Assigned to Plan Check Engineer 12/21/2023 MICHAEL LOPEZ
Assigned to Zoning Architect 12/21/2023 MICHAEL LOPEZ
Corrections Issued 1/3/2024 MICHAEL LOPEZ
Quality Review Completed 1/3/2024 PRANITA SHAH
Applicant returned to address corrections 6/12/2024 MICHAEL LOPEZ
Plan Check Approved 7/16/2024 MICHAEL LOPEZ
Issued 7/30/2024 APPLICANT
CofO in Progress 3/14/2025 TIMOTHY POWELL
Permit Finaled 3/17/2025 ERNESTO CORRAL
CofO Issued 3/17/2025 ERNESTO CORRAL
Permit Finaled 3/17/2025 ERNESTO CORRAL

Permit Application Clearance Information

Sewer availability Cleared 2/16/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 2/20/2024 JUSTIN BICOL
"D" conditions Cleared 2/23/2024 DAVID URITA
Specific Plan Cleared 2/23/2024 DAVID URITA
ZA Case Cleared 2/23/2024 DAVID URITA
ZA Case Cleared 2/23/2024 DAVID URITA
ZA Case Cleared 2/23/2024 DAVID URITA
City Hist. Cultural Monument Cleared 3/6/2024 RAFAEL FONTES
Historic Resource Verification Cleared 3/6/2024 RAFAEL FONTES
Historic monument Cleared 3/6/2024 RAFAEL FONTES
Redevelopment Project Area Cleared 3/22/2024 YASMINE BASHIRI
DAS Clearance Cleared 5/21/2024 Lawrence Quirante
Zoning Plan Check Cleared 7/16/2024 Lawrence Quirante

Contact Information

Contractor Ramirez Ricky; Lic. No.: 800586-B       ,
Engineer Hakemi,, Fahim; Lic. No.: S5160 26582 WHITE OAKS DRIVE      LAGUNA HILLS, CA 92653

Inspector Information

TIMOTHY POWELL, (213) 482-0360 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Drywall Nailing 10/24/2024 Partial Inspection TIMOTHY POWELL
Drywall Nailing 10/25/2024 Approved TIMOTHY POWELL
Wood Frame 10/25/2024 Approved TIMOTHY POWELL
Drywall Nailing 10/28/2024 Not Ready for Inspection TIMOTHY POWELL
Final 11/21/2024 Partial Inspection TIMOTHY POWELL
Reinforced Masonry Frame 11/21/2024 Approved TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 11/21/2024 SGSOV Not Ready TIMOTHY POWELL
Smoke Detectors 11/21/2024 Not Ready for Inspection TIMOTHY POWELL
Drywall Nailing 12/3/2024 Not Ready for Inspection RAFAEL CORTES
Final 12/3/2024 Partial Inspection TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 12/3/2024 SGSOV Not Ready TIMOTHY POWELL
Smoke Detectors 12/3/2024 Not Ready for Inspection TIMOTHY POWELL
Special/Order Compliance 12/17/2024 Partial Inspection TIMOTHY POWELL
Final 3/12/2025 OK to Issue CofO TIMOTHY POWELL
SGSOV-Seismic Gas S/O Valve 3/12/2025 SGSOV No Gas TIMOTHY POWELL
Smoke Detectors 3/12/2025 Approved TIMOTHY POWELL