1420 W CARROLL AVE 90026

Certificate Information: 1420 W CARROLL AVE 90026

Application / Permit
23016-10000-41981
Plan Check / Job No.
B23LA22490
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A)
Permit Issued
Issued on 1/29/2024
Issuing Office
Current Status
CofO Issued on 1/16/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/28/2023 APPLICANT
Assigned to Plan Check Engineer 12/1/2023 ISIS ARGUETA
Corrections Issued 12/4/2023 ISIS ARGUETA
Applicant returned to address corrections 12/23/2023 ISIS ARGUETA
Plan Check Approved 1/3/2024 ISIS ARGUETA
Issued 1/29/2024 APPLICANT
CofO in Progress 1/16/2026 WILLIAM SIERRA
Permit Finaled 1/16/2026 DEROLD HAUFF
CofO Issued 1/16/2026 DEROLD HAUFF
Permit Finaled 1/16/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/12/2023 DAVID LOPEZ
Sewer availability Cleared 12/12/2023 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 12/19/2023 DAVID LOPEZ
Grading Pre-Inspection Cleared 12/23/2023 ISIS ARGUETA
Hist. Property Cntrct Mgr Appr Cleared 12/29/2023 LAMBERT GIESSINGER
Historic monument Cleared 12/29/2023 LAMBERT GIESSINGER

Contact Information

Contractor Christopher Williams; Lic. No.: 711380-B       ,
Contractor Williams Christopher; Lic. No.: 711380-B       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/23/2024 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 3/18/2024 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 3/29/2024 Corrections Issued THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 5/6/2024 Corrections Issued BRENDAN MORELLI
Floor/Roof Diaphrgm/Shear Wall 8/23/2024 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 9/4/2024 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 9/4/2024 Corrections Issued HAMIK HARTOUNIAN
Underground Mechanical 9/4/2024 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 10/18/2024 Corrections Issued LUIS CASTRO
PLUMBING-Rough 10/18/2024 Corrections Issued LUIS CASTRO
Wood Frame 10/18/2024 Not Ready for Inspection LUIS CASTRO
ELECTRICAL-Rough 10/21/2024 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/21/2024 Partial Approval HAMIK HARTOUNIAN
HVAC-Rough 10/21/2024 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/29/2024 Partial Approval LUIS CASTRO
Green Building Rough 10/29/2024 Approved LUIS CASTRO
HVAC-Rough 10/29/2024 Approved LUIS CASTRO
Interior/Exterior Lathing 10/29/2024 Corrections Issued LUIS CASTRO
MERV13>=Rough 10/29/2024 Approved LUIS CASTRO
METHANE-Rough 10/29/2024 Approved LUIS CASTRO
PLUMBING-Rough 10/29/2024 Approved LUIS CASTRO
BUILDING-Rough-Frame 11/7/2024 Approved LUIS CASTRO
Insulation 11/7/2024 Approved LUIS CASTRO
Interior/Exterior Lathing 11/7/2024 Partial Approval LUIS CASTRO
Drywall Nailing 11/13/2024 Approved LUIS CASTRO
Interior/Exterior Lathing 11/25/2024 Approved ANTHONY RAMOS
Shower Pan 11/25/2024 Approved ANTHONY RAMOS
Final 7/28/2025 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 7/28/2025 Corrections Issued HAMIK HARTOUNIAN
MERV13>=Final 7/28/2025 Not Ready for Inspection HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 7/28/2025 SGSOV No Gas HAMIK HARTOUNIAN
Smoke Detectors 7/28/2025 Approved HAMIK HARTOUNIAN
Final 10/14/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Green Building Final 10/14/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
MERV13>=Final 10/14/2025 Approved ALIZAH MAYAGOITIA
Final 1/15/2026 OK to Issue CofO WILLIAM SIERRA
Green Building Final 1/15/2026 Approved WILLIAM SIERRA