2108 S MALCOLM AVE 90025
Certificate Information: 2108 S MALCOLM AVE 90025
- Application / Permit
- 23016-10000-41509
- Plan Check / Job No.
- B23LA22260
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE TO AN ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 12/26/2023
- Issuing Office
- Current Status
- CofO Issued on 5/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/29/2023 | MOHAMMAD ESMAILI |
| Corrections Issued | 11/30/2023 | MOHAMMAD ESMAILI |
| Applicant returned to address corrections | 12/21/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 12/25/2023 | DANIEL ABRAMYAN |
| Issued | 12/26/2023 | APPLICANT |
| CofO in Progress | 4/29/2024 | ASHLEY THOMPSON |
| Permit Finaled | 5/6/2024 | DANIEL ORRANTE |
| Permit Finaled | 5/6/2024 | DANIEL ORRANTE |
| CofO Issued | 5/6/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/6/2023 | LIAM ODONOVAN |
| Sewer availability | Cleared | 12/6/2023 | LIAM ODONOVAN |
| Eng Process Fee Ord 176,300 | Cleared | 12/7/2023 | LIAM ODONOVAN |
| Specific Plan | Cleared | 12/12/2023 | FREDDY GARCIA |
| Grading Pre-Inspection | Cleared | 12/20/2023 | MICHAEL TEMPLE |
Contact Information
| Architect | Hanna,, Remon; Lic. No.: NA36271 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 1/30/2024 | Partial Approval | BEN MOLSTAD |
| Footing/Foundation/Slab | 1/30/2024 | Approved | BEN MOLSTAD |
| Sewer | 1/30/2024 | Partial Approval | BEN MOLSTAD |
| Special/Order Compliance | 1/30/2024 | Partial Approval | ASHLEY THOMPSON |
| Rough-Elec/Plmb/HVAC | 2/9/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Underground Mechanical | 2/9/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 2/13/2024 | Partial Approval | ASHLEY THOMPSON |
| PLUMBING-Rough | 2/13/2024 | Approved | ASHLEY THOMPSON |
| Underground Mechanical | 2/13/2024 | Partial Approval | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 2/14/2024 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Rough | 2/14/2024 | Corrections Issued | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 2/16/2024 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Rough | 2/16/2024 | Partial Approval | MEL KHACHATOURIAN |
| Green Building Rough | 2/16/2024 | Approved | MEL KHACHATOURIAN |
| HVAC-Rough | 2/16/2024 | Approved | MEL KHACHATOURIAN |
| Insulation | 2/16/2024 | Partial Approval | MEL KHACHATOURIAN |
| METHANE-Rough | 2/16/2024 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 2/21/2024 | Approved | ASHLEY THOMPSON |
| Insulation | 2/21/2024 | Approved | ASHLEY THOMPSON |
| Drywall Nailing | 2/23/2024 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 2/23/2024 | Approved | MEL KHACHATOURIAN |
| Final | 4/18/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 4/18/2024 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| Smoke Detectors | 4/18/2024 | Approved | OGANES TARAKHCHYAN |
| Final | 4/26/2024 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Final | 4/26/2024 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 4/26/2024 | SGSOV Approved | ASHLEY THOMPSON |
| Final | 4/29/2024 | OK to Issue CofO | ASHLEY THOMPSON |