1543 W 14TH ST 90732

Certificate Information: 1543 W 14TH ST 90732

Application / Permit
23016-10000-41484
Plan Check / Job No.
B23LA22250
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel existing single-family dwelling with new addition to create bathroom and closet.
Permit Issued
Issued on 12/30/2023
Issuing Office
Current Status
CofO Issued on 3/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/25/2023 APPLICANT
Assigned to Plan Check Engineer 11/28/2023 ALEC MOUSAKHANIAN
Corrections Issued 11/29/2023 ALEC MOUSAKHANIAN
Plan Check Approved 12/28/2023 ALEC MOUSAKHANIAN
Issued 12/30/2023 APPLICANT
CofO in Progress 3/18/2025 JOSEPH MCGARRY
Permit Finaled 3/18/2025 ANSON MAGLASANG
CofO Issued 3/18/2025 ANSON MAGLASANG
Permit Finaled 3/18/2025 ANSON MAGLASANG

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/29/2023 JILVER MAZARIEGOS
Grading Pre-Inspection Cleared 11/29/2023 ALEC MOUSAKHANIAN
Roof/Waste drainage to street Cleared 11/29/2023 JILVER MAZARIEGOS

Contact Information

Architect Baron,, Gabriel; Lic. No.: NA38679       ,
Contractor Owner-Builder       ,
Engineer Roberts,, Jeffrey Allan; Lic. No.: NA56881       ,

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/16/2024 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 3/5/2024 Partial Approval JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 4/11/2024 Conditional Approval JAMES CHAVEZ
Special/Order Compliance 4/11/2024 Corrections Issued JAMES CHAVEZ
Deputy Wood Construction 4/17/2024 Conditional Approval JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 4/22/2024 Not Ready for Inspection JAMES CHAVEZ
Floor/Roof Diaphrgm/Shear Wall 5/23/2024 Partial Approval JAMES CHAVEZ
Interior/Exterior Lathing 5/23/2024 Partial Approval JAMES CHAVEZ
ELECTRICAL-Rough 6/4/2024 Corrections Issued JAMES CHAVEZ
HVAC-Rough 6/4/2024 Corrections Issued JAMES CHAVEZ
PLUMBING-Rough 6/4/2024 Approved JAMES CHAVEZ
ELECTRICAL-Rough 6/17/2024 Approved JAMES CHAVEZ
HVAC-Rough 6/17/2024 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 6/25/2024 Approved JAMES CHAVEZ
Insulation 6/25/2024 Approved JAMES CHAVEZ
Shower Pan 6/25/2024 Approved JAMES CHAVEZ
Drywall Nailing 7/8/2024 Approved JAMES CHAVEZ
Interior/Exterior Lathing 7/8/2024 Partial Approval JAMES CHAVEZ
Final 3/3/2025 Corrections Issued JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 3/3/2025 SGSOV Not Ready JOSEPH MCGARRY
Smoke Detectors 3/3/2025 Approved JOSEPH MCGARRY
Final 3/14/2025 OK to Issue CofO JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 3/14/2025 SGSOV Approved JOSEPH MCGARRY