3823-3825 S WALTON AVE 90037
Certificate Information: 3823-3825 S WALTON AVE 90037
- Application / Permit
- 23016-10000-41338
- Plan Check / Job No.
- B23LA22213
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EPLAN - REPLACE (E) WINDOWS, STAIR, AND NEW 62 SF PATIO COVER AT THE REAR EXTERIOR AND NEW UNCOVERED WALKING DECK AND DOOR INSTALLATION AT THE FRONT EXTERIOR - (N) HEATING AND AC UNITS *CONSTRUCTION PER WFPP*
- Permit Issued
- Issued on 3/21/2024
- Issuing Office
- Current Status
- CofO Issued on 6/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/27/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/27/2023 | HANS SANTIAGO |
| Corrections Issued | 11/27/2023 | HANS SANTIAGO |
| Applicant returned to address corrections | 3/13/2024 | HANS SANTIAGO |
| Plan Check Approved | 3/20/2024 | ANDREW SANTIAGO |
| Issued | 3/21/2024 | APPLICANT |
| CofO in Progress | 6/6/2024 | SABAS ALONSO |
| Permit Finaled | 6/10/2024 | DEROLD HAUFF |
| CofO Issued | 6/10/2024 | DEROLD HAUFF |
| Permit Finaled | 6/10/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 3/15/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/18/2024 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 4/10/2024 | Not Ready for Inspection | SABAS ALONSO |
| Final | 4/10/2024 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 4/10/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 4/10/2024 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 4/10/2024 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 4/10/2024 | SGSOV Not Ready | SABAS ALONSO |
| Smoke Detectors | 4/10/2024 | Not Ready for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 4/16/2024 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 4/16/2024 | Approved | SABAS ALONSO |
| Final | 4/16/2024 | Not Ready for Inspection | SABAS ALONSO |
| Footing/Foundation/Slab | 4/16/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 4/16/2024 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 4/16/2024 | Approved | SABAS ALONSO |
| Insulation | 4/16/2024 | Not Ready for Inspection | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 4/16/2024 | SGSOV Not Ready | SABAS ALONSO |
| PLUMBING-Rough | 4/23/2024 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/20/2024 | Approved | SABAS ALONSO |
| Green Building Rough | 5/20/2024 | Approved | SABAS ALONSO |
| Insulation | 5/20/2024 | Approved | SABAS ALONSO |
| Drywall Nailing | 5/24/2024 | Approved | SABAS ALONSO |
| Final | 5/24/2024 | Not Ready for Inspection | SABAS ALONSO |
| Final | 5/29/2024 | Corrections Issued | SABAS ALONSO |
| Final | 6/5/2024 | OK to Issue CofO | SABAS ALONSO |
| Green Building Final | 6/5/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 6/5/2024 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 6/5/2024 | Approved | SABAS ALONSO |