143 S AVENUE 54 90042
Certificate Information: 143 S AVENUE 54 90042
- Application / Permit
- 23016-10000-40978
- Plan Check / Job No.
- B23LA21995
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH 93. INSTALL (3) MOMENT FRAMES
- Permit Issued
- Issued on 6/12/2024
- Issuing Office
- Metro
- Current Status
- Issued on 6/12/2024
Permit Application Status History
| Submitted | 11/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/22/2023 | VARAND SARKISIAN |
| Corrections Issued | 12/1/2023 | VARAND SARKISIAN |
| Quality Review Completed | 12/6/2023 | HANS SANTIAGO |
| Building Plans Picked Up | 12/6/2023 | APPLICANT |
| Applicant returned to address corrections | 2/1/2024 | VARAND SARKISIAN |
| Plan Check Approved | 2/23/2024 | VARAND SARKISIAN |
| Issued | 6/12/2024 | APPLICANT |
Permit Application Clearance Information
| HPOZ | Cleared | 12/14/2023 | MICAELA TORRES-GIL |
| ZI | Cleared | 2/16/2024 | PABLO ESTRADA |
| Tenant Habitability Plan | Cleared | 6/5/2024 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Omega Structural Inc; Lic. No.: 998075-B | 4269 S HARVARD BOULEVARD LOS ANGELES, CA 90062 |
| Engineer | Zhuang,, Wenbin; Lic. No.: S5236 | 205 S CHAPEL AVE #D-1 ALHAMBRA, CA 91801 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 8/9/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Pre-Inspection | 8/9/2024 | Partial Inspection | RAMAZANALI ALMASI |
| SGSOV-Seismic Gas S/O Valve | 8/9/2024 | SGSOV Not Ready | RAMAZANALI ALMASI |
| Smoke Detectors | 8/9/2024 | Not Ready for Inspection | RAMAZANALI ALMASI |
| Excavation/Setback/Form/Re-Bar | 7/30/2025 | Approved | DARRYL ARNOLD |
| Wood Frame | 1/14/2026 | Partial Approval | ALFREDO LOPEZ |
| Wood Frame | 2/17/2026 | No Access for Inspection | ALFREDO LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2026 | Corrections Issued | DARRYL ARNOLD |
| Interior/Exterior Lathing | 3/23/2026 | Not Ready for Inspection | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2026 | Not Ready for Inspection | DARRYL ARNOLD |
| Interior/Exterior Lathing | 3/24/2026 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 4/24/2026 | Partial Approval | JEROME BLACKWOOD |