4341 N GRIFFIN AVE 90031
Certificate Information: 4341 N GRIFFIN AVE 90031
- Application / Permit
- 23016-10000-40917
- Plan Check / Job No.
- B23LA00327
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan CONVERT (E) CABANA TO ADU. 1 of 2 ADUs. DETACHED ADU PER GCS 65852.2(E)(1)(D) and LAMC 12.22 A.33 (c), (d), and (g). INVESTIGATION FEE DUE: Investigation fee due. Code Enforcement Order to Comply issued with effective date 02/14/2019 by Inspector ARIS ALLAHVERDIAN at phone# (213)482-6878. CEIS Case Number is 840373. Payment of investigation fee due at time of permit issuance. NOTE: Investigation fee is minimum $400.00 or double the permit fee which ever is greater.
- Permit Issued
- Issued on 3/8/2024
- Issuing Office
- Current Status
- CofO Issued on 12/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/9/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 2/16/2023 | ADRIANA LOPEZ |
| Corrections Issued | 3/29/2023 | ADRIANA LOPEZ |
| Quality Review Completed | 5/8/2023 | QUAN NGHIEM |
| Applicant returned to address corrections | 10/4/2023 | ADRIANA LOPEZ |
| Applicant returned to address corrections | 11/22/2023 | ADRIANA LOPEZ |
| Plan Check Approved | 2/16/2024 | ADRIANA LOPEZ |
| Issued | 3/8/2024 | APPLICANT |
| CofO in Progress | 10/3/2025 | FERMIN RUBIO |
| CofO in Progress | 11/21/2025 | FERMIN RUBIO |
| Permit Finaled | 12/8/2025 | DANIEL SANCHEZ |
| CofO Issued | 12/8/2025 | DANIEL SANCHEZ |
| Permit Finaled | 12/8/2025 | DANIEL SANCHEZ |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 11/19/2023 | ADRIANA LOPEZ |
| CPC | Cleared | 1/31/2024 | MICAELA TORRES-GIL |
| HPOZ | Cleared | 1/31/2024 | MICAELA TORRES-GIL |
| Miscellaneous | Cleared | 1/31/2024 | MICAELA TORRES-GIL |
| ZI | Cleared | 1/31/2024 | LINDA LOU |
| Low Impact Development (LID) | Cleared | 2/1/2024 | SAMUEL LINN |
| Roof/Waste drainage to street | Cleared | 2/3/2024 | CELINA MORENO |
| Sewer availability | Cleared | 2/3/2024 | CELINA MORENO |
| Address approval | Cleared | 2/9/2024 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 2/9/2024 | CELINA MORENO |
| "Q" conditions | Cleared | 2/13/2024 | JASON CHAN |
| Grading Pre-Inspection | Cleared | 2/16/2024 | ADRIANA LOPEZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gonzalez,, Fernando Francisco; Lic. No.: NA53256 | , |
Inspector Information
| THOMAS WILLIS, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| JEFFREY CHRISTIAN, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| FERMIN RUBIO, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| JACOB SEGURA, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| CLAUDIO MORENO, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK RUDE, (213) 252-3038 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/28/2024 | Not Ready for Inspection | JONATHAN FRANCHINI |
| Sewer | 6/28/2024 | Not Ready for Inspection | JONATHAN FRANCHINI |
| Underground Mechanical | 6/28/2024 | Not Ready for Inspection | JONATHAN FRANCHINI |
| BUILDING-Rough-Frame | 8/15/2024 | Not Ready for Inspection | JACOB SEGURA |
| Deputy Drilled-In Anchors | 8/15/2024 | No Access for Inspection | JACOB SEGURA |
| ELECTRICAL-Rough | 8/15/2024 | Not Ready for Inspection | JACOB SEGURA |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2024 | Not Ready for Inspection | JACOB SEGURA |
| Gas Test | 8/15/2024 | Not Ready for Inspection | JACOB SEGURA |
| Green Building Rough | 8/15/2024 | Not Ready for Inspection | JACOB SEGURA |
| HVAC-Rough | 8/15/2024 | Not Ready for Inspection | JACOB SEGURA |
| MERV13>=Rough | 8/15/2024 | Not Ready for Inspection | JACOB SEGURA |
| PLUMBING-Rough | 8/15/2024 | Not Ready for Inspection | JACOB SEGURA |
| Verify Sprinkler Sign Off | 8/15/2024 | Not Ready for Inspection | JACOB SEGURA |
| BUILDING-Rough-Frame | 9/3/2024 | Corrections Issued | ROBERT MINASSIANS |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2024 | Corrections Issued | ROBERT MINASSIANS |
| Green Building Rough | 9/3/2024 | Corrections Issued | ROBERT MINASSIANS |
| MERV13>=Rough | 9/3/2024 | Approved | ROBERT MINASSIANS |
| Rough-Elec/Plmb/HVAC | 9/3/2024 | Corrections Issued | ROBERT MINASSIANS |
| Verify Sprinkler Sign Off | 9/3/2024 | Approved | ROBERT MINASSIANS |
| ELECTRICAL-Rough | 9/9/2024 | Corrections Issued | FERMIN RUBIO |
| PLUMBING-Rough | 9/9/2024 | Corrections Issued | FERMIN RUBIO |
| Rough-Elec/Plmb/HVAC | 9/9/2024 | Not Ready for Inspection | FERMIN RUBIO |
| Wood Frame | 9/9/2024 | Corrections Issued | FERMIN RUBIO |
| Insulation | 11/4/2024 | No Access for Inspection | JACOB SEGURA |
| Interior/Exterior Lathing | 11/4/2024 | Corrections Issued | JACOB SEGURA |
| BUILDING-Rough-Frame | 11/6/2024 | Corrections Issued | FERMIN RUBIO |
| Green Building Rough | 11/6/2024 | Not Ready for Inspection | FERMIN RUBIO |
| Rough-Elec/Plmb/HVAC | 11/6/2024 | Corrections Issued | FERMIN RUBIO |
| Special/Order Compliance | 11/6/2024 | Approved | ROBERT MINASSIANS |
| BUILDING-Rough-Frame | 11/19/2024 | Conditional Approval | FERMIN RUBIO |
| ELECTRICAL-Rough | 11/19/2024 | Approved | FERMIN RUBIO |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2024 | Conditional Approval | FERMIN RUBIO |
| Green Building Rough | 11/19/2024 | Not Ready for Inspection | FERMIN RUBIO |
| HVAC-Rough | 11/19/2024 | Corrections Issued | FERMIN RUBIO |
| Insulation | 11/19/2024 | Approved | FERMIN RUBIO |
| PLUMBING-Rough | 11/19/2024 | Approved | FERMIN RUBIO |
| Rough-Elec/Plmb/HVAC | 11/19/2024 | Conditional Approval | FERMIN RUBIO |
| Drywall Nailing | 12/5/2024 | No Access for Inspection | JACOB SEGURA |
| Drywall Nailing | 12/12/2024 | Conditional Approval | JACOB SEGURA |
| Special/Order Compliance | 12/12/2024 | Approved | ROBERT MINASSIANS |
| Interior/Exterior Lathing | 1/13/2025 | Partial Approval | FERMIN RUBIO |
| BUILDING-Rough-Frame | 2/12/2025 | Conditional Approval | FERMIN RUBIO |
| Final | 2/12/2025 | Corrections Issued | FERMIN RUBIO |
| Green Building Final | 2/12/2025 | Corrections Issued | FERMIN RUBIO |
| Green Building Rough | 2/12/2025 | Not Ready for Inspection | FERMIN RUBIO |
| MERV13>=Final | 2/12/2025 | Approved | FERMIN RUBIO |
| SGSOV-Seismic Gas S/O Valve | 2/12/2025 | SGSOV Not Ready | FERMIN RUBIO |
| Smoke Detectors | 2/12/2025 | Conditional Approval | FERMIN RUBIO |
| BUILDING-Rough-Frame | 2/19/2025 | Conditional Approval | FERMIN RUBIO |
| Final | 2/19/2025 | Corrections Issued | FERMIN RUBIO |
| Green Building Final | 2/19/2025 | Conditional Approval | FERMIN RUBIO |
| Green Building Rough | 2/19/2025 | Approved | FERMIN RUBIO |
| SGSOV-Seismic Gas S/O Valve | 2/19/2025 | SGSOV Not Ready | FERMIN RUBIO |
| Smoke Detectors | 2/19/2025 | Approved | FERMIN RUBIO |
| BUILDING-Rough-Frame | 2/24/2025 | Approved | FERMIN RUBIO |
| Final | 2/24/2025 | OK to Issue CofO | FERMIN RUBIO |
| Green Building Final | 2/24/2025 | Approved | FERMIN RUBIO |
| SGSOV-Seismic Gas S/O Valve | 2/24/2025 | SGSOV Approved | FERMIN RUBIO |
| Gas Test | 10/23/2025 | Approved | FERMIN RUBIO |
| ELECTRICAL-Final | 11/21/2025 | Approved | FERMIN RUBIO |
| Final | 11/21/2025 | OK to Issue CofO | FERMIN RUBIO |
| HVAC-Final | 11/21/2025 | Approved | FERMIN RUBIO |
| PLUMBING-Final | 11/21/2025 | Approved | FERMIN RUBIO |
| Rough-Elec/Plmb/HVAC | 11/21/2025 | Approved | FERMIN RUBIO |