3947 S TIVOLI AVE 90066

Certificate Information: 3947 S TIVOLI AVE 90066

Application / Permit
23016-10000-40902
Plan Check / Job No.
B23LA21935
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan CONVERT EX. DETACHED GARAGE AND UNPERMITTED SECOND FLOOR LOFT BUILT PRIOR TO JAN 1, 2018 INTO ACCESSORY DWELLING UNIT PER GCS 65852.23.
Permit Issued
Issued on 3/13/2024
Issuing Office
Current Status
CofO Issued on 12/3/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/19/2023 APPLICANT
Assigned to Plan Check Engineer 11/22/2023 MIROOSH KHACHATOORIAN
Corrections Issued 11/23/2023 MIROOSH KHACHATOORIAN
Applicant returned to address corrections 2/28/2024 ISIS ARGUETA
Applicant returned to address corrections 3/5/2024 ISIS ARGUETA
Plan Check Approved 3/12/2024 ROSENDO MEDINA
Issued 3/13/2024 APPLICANT
CofO in Progress 11/12/2024 ARAM AVEDISIAN
Permit Finaled 12/3/2024 RICHARD STEINBACH
CofO Issued 12/3/2024 RICHARD STEINBACH
Permit Finaled 12/3/2024 RICHARD STEINBACH

Permit Application Clearance Information

Specific Plan Cleared 11/28/2023 ALESSANDRO MERCURI
Address approval Cleared 11/30/2023 ANDREA SAINT-ANTONIN
Sewer availability Cleared 11/30/2023 ANDREA SAINT-ANTONIN
Eng Process Fee Ord 176,300 Cleared 12/1/2023 ANDREA SAINT-ANTONIN

Contact Information

Contractor Owner-Builder       ,
Engineer Bartelle,, Kristofer Grimm; Lic. No.: C84617 19900 ACRE ST      LOS ANGELES, CA 91324

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/18/2024 Partial Inspection HERBERT GIRON
Deputy Drilled-In Anchors 5/8/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 5/22/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/22/2024 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 5/22/2024 Approved JESUS RODRIGUEZ
Green Building Rough 5/22/2024 Not Ready for Inspection JESUS RODRIGUEZ
Interior/Exterior Lathing 5/22/2024 Approved JESUS RODRIGUEZ
PLUMBING-Rough 5/22/2024 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/1/2024 Corrections Issued JESUS RODRIGUEZ
Green Building Rough 8/1/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 8/1/2024 Conditional Approval JESUS RODRIGUEZ
BUILDING-Rough-Frame 8/20/2024 Approved JESUS RODRIGUEZ
Drywall Nailing 8/20/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/20/2024 Approved JESUS RODRIGUEZ
Green Building Rough 8/20/2024 Approved JESUS RODRIGUEZ
HVAC-Rough 8/20/2024 Approved JESUS RODRIGUEZ
Insulation 8/20/2024 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 8/20/2024 Approved JESUS RODRIGUEZ
PLUMBING-Rough 8/20/2024 Approved JESUS RODRIGUEZ
Final 10/30/2024 Corrections Issued JESUS PINEDA
Green Building Final 10/30/2024 Corrections Issued JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 10/30/2024 SGSOV Approved JESUS PINEDA
Smoke Detectors 10/30/2024 Approved JESUS PINEDA
Final 11/12/2024 OK to Issue CofO ARAM AVEDISIAN
Green Building Final 11/12/2024 Approved ARAM AVEDISIAN