3850 N PORTOLA AVE 90032

Certificate Information: 3850 N PORTOLA AVE 90032

Application / Permit
23016-10000-40901
Plan Check / Job No.
B23LA21931
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT TO COMPLY WITH GCS 65852.2(e)(1)(A) PER ENGINEERING
Permit Issued
Issued on 1/31/2024
Issuing Office
Current Status
CofO Issued on 6/17/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/21/2023 APPLICANT
Assigned to Plan Check Engineer 11/22/2023 ALFRED RAMIREZ
Corrections Issued 11/22/2023 ALFRED RAMIREZ
Plan Check Approved 1/31/2024 ALFRED RAMIREZ
Issued 1/31/2024 APPLICANT
CofO in Progress 6/12/2024 LILIANA PORTILLO
CofO Issued 6/17/2024 DEROLD HAUFF
Permit Finaled 6/17/2024 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/29/2023 JUSTIN BICOL
Grading Pre-Inspection Cleared 11/29/2023 ALEXANDER HELFER
Sewer availability Cleared 11/29/2023 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 11/30/2023 JUSTIN BICOL

Contact Information

Contractor L A Green Designs; Lic. No.: 988980-B       ,
Contractor Mijoma Inc; Lic. No.: 988980-B       ,
Engineer Espino,, Manuel A; Lic. No.: NA55526       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/2/2024 Partial Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 2/7/2024 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 2/7/2024 Approved ALIZAH MAYAGOITIA
Green Building Rough 2/7/2024 Approved ALIZAH MAYAGOITIA
HVAC-Rough 2/7/2024 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 2/7/2024 Approved ALIZAH MAYAGOITIA
HVAC-Rough 2/29/2024 Corrections Issued LILIANA PORTILLO
Insulation 2/29/2024 Approved LILIANA PORTILLO
Interior/Exterior Lathing 2/29/2024 Approved LILIANA PORTILLO
Shower Pan 2/29/2024 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/28/2024 Corrections Issued LILIANA PORTILLO
HVAC-Rough 3/28/2024 Approved LILIANA PORTILLO
Drywall Nailing 4/10/2024 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 4/10/2024 Approved LILIANA PORTILLO
Final 6/7/2024 Corrections Issued LILIANA PORTILLO
Green Building Final 6/7/2024 Corrections Issued LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 6/7/2024 SGSOV Not Required LILIANA PORTILLO
Smoke Detectors 6/7/2024 Approved LILIANA PORTILLO
ELECTRICAL-Final 6/11/2024 Approved LILIANA PORTILLO
Final 6/11/2024 OK to Issue CofO LILIANA PORTILLO
Green Building Final 6/11/2024 Approved LILIANA PORTILLO
HVAC-Final 6/11/2024 Approved LILIANA PORTILLO
PLUMBING-Final 6/11/2024 Approved LILIANA PORTILLO