2602 S HOLT AVE 90034

Certificate Information: 2602 S HOLT AVE 90034

Application / Permit
23016-10000-40850
Plan Check / Job No.
B23LA21898
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN REPAIR EXISTING SINGLE-FAMILY DWELLING DUE TO FIRE DAMAGE ALONG WITH INTEROR REMODEL CREATING NEW FLOOR PLAN
Permit Issued
Issued on 7/9/2024
Issuing Office
Current Status
Permit Finaled on 5/15/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/28/2023 APPLICANT
Assigned to Plan Check Engineer 12/1/2023 ALEC MOUSAKHANIAN
Corrections Issued 12/4/2023 ALEC MOUSAKHANIAN
Applicant returned to address corrections 1/2/2024 KAMYAR EMAMI
Applicant returned to address corrections 2/22/2024 MOHAMMAD ESMAILI
Applicant returned to address corrections 2/29/2024 MOHAMMAD ESMAILI
Plan Check Approved 3/2/2024 MOHAMMAD ESMAILI
Issued 7/9/2024 APPLICANT
Permit Finaled 5/15/2025 BOBBY KEY

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor C M J Construction Inc; Lic. No.: 1095617-B       ,
Engineer Kim,, Hong Kook; Lic. No.: NA64529       ,

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/9/2024 Approved MEL KHACHATOURIAN
Deputy Drilled-In Anchors 11/6/2024 Conditional Approval BOBBY KEY
Footing/Foundation/Slab 11/7/2024 Corrections Issued MEL KHACHATOURIAN
Footing/Foundation/Slab 12/18/2024 Corrections Issued DANIEL VERA
Footing/Foundation/Slab 1/6/2025 Approved BOBBY KEY
PLUMBING-Rough 1/6/2025 Partial Approval BOBBY KEY
Special/Order Compliance 1/6/2025 Partial Inspection JAYLIN GRAVITTE
Deputy Drilled-In Anchors 1/30/2025 Approved ARAM AVEDISIAN
Deputy Wood Construction 4/1/2025 Conditional Approval EVAN COOPER
BUILDING-Rough-Frame 4/4/2025 Corrections Issued EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/4/2025 Partial Approval EVAN COOPER
HVAC-Rough 4/4/2025 Corrections Issued EVAN COOPER
MERV13>=Rough 4/4/2025 Approved EVAN COOPER
PLUMBING-Rough 4/4/2025 Approved EVAN COOPER
BUILDING-Rough-Frame 5/2/2025 Conditional Approval EVAN COOPER
ELECTRICAL-Rough 5/2/2025 Approved EVAN COOPER
HVAC-Rough 5/2/2025 Not Ready for Inspection EVAN COOPER