1330 W PICO BLVD 209 90015
Certificate Information: 1330 W PICO BLVD 209 90015
- Application / Permit
- 23016-10000-40816
- Plan Check / Job No.
- B23LA21881
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (22) Storage Building
- Work Description
- EPLAN EXPEDITE Change of Use of a 2 story, Type I, 200'x500' irregularly shaped Industrial Building with 256 parking spaces to a Self-Storage Facility
- Permit Issued
- Issued on 2/25/2025
- Issuing Office
- Current Status
- Issued on 2/25/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/20/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/21/2023 | QUAN NGHIEM |
| Assigned to Zoning Architect | 12/1/2023 | QUAN NGHIEM |
| Corrections Issued | 1/2/2024 | QUAN NGHIEM |
| Quality Review Completed | 1/2/2024 | PETER KIM |
| Applicant returned to address corrections | 2/16/2024 | QUAN NGHIEM |
| Applicant returned to address corrections | 3/1/2024 | QUAN NGHIEM |
| Applicant returned to address corrections | 9/24/2024 | QUAN NGHIEM |
| Plan Check Approved | 12/20/2024 | QUAN NGHIEM |
| Issued | 2/25/2025 | APPLICANT |
Permit Application Clearance Information
| Historic monument | Cleared | 1/19/2024 | DAMIAN GATTO |
| Sewer availability | Cleared | 1/29/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2024 | WALLIE JONG |
| Green Code | Cleared | 12/6/2024 | Rosendo Medina |
| Address approval | Cleared | 12/11/2024 | DAVID LOPEZ |
| Miscellaneous | Cleared | 12/11/2024 | ROSALINDA MEZA |
| DAS Clearance | Cleared | 12/16/2024 | ELIZABETH TOMS |
| Zoning Plan Check | Cleared | 12/20/2024 | QUAN NGHIEM |
Contact Information
| Architect | Herman,, Richard Sigmund; Lic. No.: NA9727 | , |
| Contractor | Vertical Construction Inc; Lic. No.: 409490-B | , |
| Engineer | Ales,, Joseph Michael; Lic. No.: S5282 | 300 SO ORANGE AVE STE 1200 ORLANDO, FL 32801 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/10/2025 | Partial Approval | JEROME BLACKWOOD |
| Deputy Drilled-In Anchors | 6/2/2025 | Conditional Approval | JOEY BUCHANAN |
| Green Building Rough | 6/24/2025 | Partial Inspection | JEROME BLACKWOOD |
| METHANE-Rough | 6/24/2025 | Partial Approval | JEROME BLACKWOOD |
| Reinforced Concrete Frame | 6/24/2025 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 10/2/2025 | Partial Approval | PAUL BAZERKANIAN |
| Masonry Wall/Backfill | 11/14/2025 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 12/4/2025 | Partial Approval | PAUL BAZERKANIAN |
| Excavation/Setback/Form/Re-Bar | 12/11/2025 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 12/19/2025 | Approved | RONALD JIMENEZ |
| T-Bar Ceiling | 1/22/2026 | Not Ready for Inspection | LARRY ARNICK |
| Pre-Inspection | 3/26/2026 | Partial Inspection | REGINA MENDEZ |
| T-Bar Ceiling | 3/26/2026 | Partial Approval | REGINA MENDEZ |
| Final | 5/12/2026 | Not Ready for Inspection | REGINA MENDEZ |
| Green Building Final | 5/12/2026 | Not Ready for Inspection | REGINA MENDEZ |
| Green Building Rough | 5/12/2026 | Not Ready for Inspection | REGINA MENDEZ |
| METHANE-Final | 5/12/2026 | Not Ready for Inspection | REGINA MENDEZ |
| METHANE-Rough | 5/12/2026 | Not Ready for Inspection | REGINA MENDEZ |
| Reinforced Concrete Frame | 5/12/2026 | Not Ready for Inspection | REGINA MENDEZ |
| SGSOV-Seismic Gas S/O Valve | 5/12/2026 | SGSOV Not Ready | REGINA MENDEZ |
| Smoke Detectors | 5/12/2026 | Not Ready for Inspection | REGINA MENDEZ |
| Light Gage Steel Frame | 5/19/2026 | Not Ready for Inspection | JEROME BLACKWOOD |
| Drywall Nailing | 5/22/2026 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 5/28/2026 | Partial Approval | JEROME BLACKWOOD |
| Final | 6/3/2026 | Not Ready for Inspection | JEROME BLACKWOOD |
| Green Building Final | 6/3/2026 | Not Ready for Inspection | JEROME BLACKWOOD |
| Green Building Rough | 6/3/2026 | Not Ready for Inspection | JEROME BLACKWOOD |
| METHANE-Final | 6/3/2026 | Approved | JEROME BLACKWOOD |
| METHANE-Rough | 6/3/2026 | Approved | JEROME BLACKWOOD |
| Reinforced Concrete Frame | 6/3/2026 | Not Ready for Inspection | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 6/3/2026 | SGSOV Not Ready | JEROME BLACKWOOD |
| Smoke Detectors | 6/3/2026 | Not Ready for Inspection | JEROME BLACKWOOD |