5923 1/2 S HAAS AVE 90047
Certificate Information: 5923 1/2 S HAAS AVE 90047
- Application / Permit
- 23016-10000-40380
- Plan Check / Job No.
- B23LA21819
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: SUPPLEMENTAL TO PCIS #21016-20000-25394 to Revise plans due to change in scope of work from garage conversion to ADU per CA Govt. Code 65852.2(e)(1)(A) To (N) Detached ADU Per CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g) Comply with Department Order effective date 03/14/2020. If additional assistance is needed please call Senior Inspector MICHAEL SCHULZINGER at (213)252-3962. CEIS Case Number is 896160.
- Permit Issued
- Issued on 6/3/2024
- Issuing Office
- Current Status
- Permit Finaled on 4/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/17/2023 | ALFREDO JARA |
| Corrections Issued | 11/19/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 12/1/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 12/8/2023 | ALFREDO JARA |
| Applicant returned to address corrections | 5/25/2024 | AMY GUEVARRA |
| Plan Check Approved | 6/2/2024 | AMY GUEVARRA |
| Issued | 6/3/2024 | APPLICANT |
| CofO in Progress | 3/27/2025 | GABRIEL HERRERA |
| Permit Finaled-Status Void | 4/7/2025 | HAGOP BADOSSIAN |
| No Progress | 4/7/2025 | HAGOP BADOSSIAN |
| CofO in Progress | 4/7/2025 | HAGOP BADOSSIAN |
| Re-Activate Permit | 4/8/2025 | HAGOP BADOSSIAN |
| Permit Finaled | 4/8/2025 | HAGOP BADOSSIAN |
Permit Application Clearance Information
| CPC | Cleared | 2/5/2024 | ASHLEY RODARTE |
| Address approval | Cleared | 2/6/2024 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 2/22/2024 | AMBER CAMPBELL |
| Sewer availability | Cleared | 2/22/2024 | AMBER CAMPBELL |
| Construction near power lines | Cleared | 5/17/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/6/2024 | Approved | GABRIEL HERRERA |
| Excavation/Setback/Form/Re-Bar | 6/11/2024 | Approved | GABRIEL HERRERA |
| Footing/Foundation/Slab | 6/11/2024 | Approved | GABRIEL HERRERA |
| METHANE-Barrier | 6/11/2024 | Approved | GABRIEL HERRERA |
| METHANE-Subgrade | 6/11/2024 | Approved | GABRIEL HERRERA |
| Floor/Roof Diaphrgm/Shear Wall | 6/18/2024 | Approved | GABRIEL HERRERA |
| Interior/Exterior Lathing | 7/12/2024 | Approved | GABRIEL HERRERA |
| Rough-Elec/Plmb/HVAC | 7/15/2024 | Approved | GABRIEL HERRERA |
| Insulation | 7/18/2024 | Approved | GABRIEL HERRERA |
| Shower Pan | 7/18/2024 | Approved | GABRIEL HERRERA |
| Drywall Nailing | 7/19/2024 | Approved | GABRIEL HERRERA |
| Interior/Exterior Lathing | 7/19/2024 | Approved | GABRIEL HERRERA |
| Sewer | 8/2/2024 | Approved | GABRIEL HERRERA |
| Underground Mechanical | 8/2/2024 | Approved | GABRIEL HERRERA |
| BUILDING-Rough-Frame | 10/3/2024 | Approved | GABRIEL HERRERA |
| Final | 10/3/2024 | Conditional Approval | GABRIEL HERRERA |
| Green Building Final | 10/3/2024 | Approved | GABRIEL HERRERA |
| Green Building Rough | 10/3/2024 | Approved | GABRIEL HERRERA |
| METHANE-Final | 10/3/2024 | Approved | GABRIEL HERRERA |
| METHANE-Rough | 10/3/2024 | Approved | GABRIEL HERRERA |
| SGSOV-Seismic Gas S/O Valve | 10/3/2024 | SGSOV Approved | GABRIEL HERRERA |
| Service/Power Release | 10/3/2024 | Approved | GABRIEL HERRERA |
| Smoke Detectors | 10/3/2024 | Approved | GABRIEL HERRERA |
| Verify Sprinkler Sign Off | 10/3/2024 | Conditional Approval | GABRIEL HERRERA |
| Final | 3/27/2025 | OK to Issue CofO | GABRIEL HERRERA |
| Final | 4/7/2025 | Conditional Approval | HAGOP BADOSSIAN |
| Special/Order Compliance | 4/7/2025 | Conditional Approval | HAGOP BADOSSIAN |
| Final | 4/8/2025 | Permit Finaled | HAGOP BADOSSIAN |
| METHANE-Final | 4/8/2025 | Approved | HAGOP BADOSSIAN |