11001 W VENTURA BLVD 91604
Certificate Information: 11001 W VENTURA BLVD 91604
- Application / Permit
- 23016-10000-40369
- Plan Check / Job No.
- B23LA21805
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- ePlan CONVERT (E) AUTO REPAIR AREA TO BECOME PART OF (E) CONVENIENCE STORE.
- Permit Issued
- Issued on 6/6/2024
- Issuing Office
- Current Status
- CofO Issued on 11/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2023 | ARSALAN SHABESTARI |
| Assigned to Zoning Architect | 12/1/2023 | ARSALAN SHABESTARI |
| Corrections Issued | 12/4/2023 | ARSALAN SHABESTARI |
| Quality Review Completed | 12/15/2023 | SINA KHOSRAVI |
| Plan Check Approved | 3/22/2024 | ARSALAN SHABESTARI |
| Issued | 6/6/2024 | APPLICANT |
| Permit Finaled | 11/12/2025 | RICKEY JACKSON |
| CofO Issued | 11/12/2025 | RICKEY JACKSON |
| Permit Finaled | 11/12/2025 | RICKEY JACKSON |
Permit Application Clearance Information
| Specific Plan | Cleared | 1/16/2024 | SHEILA AHORAIAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 1/24/2024 | EDGAR ALCARAZ |
| Miscellaneous | Cleared | 2/19/2024 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 2/19/2024 | STEVEN WECHSLER |
| ZI | Cleared | 2/19/2024 | STEVEN WECHSLER |
| Green Code | Cleared | 2/20/2024 | Lawrence Quirante |
| Specific Plan | Cleared | 2/20/2024 | ADRINEH MELKONIAN |
| DAS Clearance | Cleared | 3/12/2024 | Lawrence Quirante |
| Zoning Plan Check | Cleared | 3/22/2024 | Lawrence Quirante |
Contact Information
| Contractor | Rsvc Company; Lic. No.: 961558-B | , |
Inspector Information
| JEFFREY FULTON, (818) 374-1132 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/21/2024 | Not Ready for Inspection | STEVEN LEVITT |
| Footing/Foundation/Slab | 12/12/2024 | Approved | STEVEN LEVITT |
| Excavation/Setback/Form/Re-Bar | 1/23/2025 | Not Ready for Inspection | STEVEN LEVITT |
| Excavation/Setback/Form/Re-Bar | 1/29/2025 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 1/29/2025 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 1/31/2025 | Partial Approval | DANNY RODRIGUEZ |
| Light Gage Steel Frame | 2/3/2025 | Partial Approval | STEVEN LEVITT |
| Drywall Nailing | 2/5/2025 | Partial Approval | STEVEN LEVITT |
| Insulation | 2/5/2025 | Approved | STEVEN LEVITT |
| Light Gage Steel Frame | 2/5/2025 | Approved | STEVEN LEVITT |
| Insulation | 2/6/2025 | Approved | STEVEN LEVITT |
| Drywall Nailing | 2/10/2025 | Partial Approval | ROBERT DAVIS |
| Drywall Nailing | 2/11/2025 | Approved | STEVEN LEVITT |
| Deputy Drilled-In Anchors | 2/12/2025 | Conditional Approval | STEVEN LEVITT |
| Excavation/Setback/Form/Re-Bar | 2/13/2025 | Approved | STEVEN LEVITT |
| T-Bar Ceiling | 2/19/2025 | Corrections Issued | STEVEN LEVITT |
| T-Bar Ceiling | 2/20/2025 | Approved | STEVEN LEVITT |
| Final | 6/30/2025 | Not Ready for Inspection | KENNETH ROBERTS |
| Green Building Final | 6/30/2025 | Not Ready for Inspection | KENNETH ROBERTS |
| Green Building Rough | 6/30/2025 | Not Ready for Inspection | KENNETH ROBERTS |
| Reinforced Masonry Frame | 6/30/2025 | Not Ready for Inspection | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 6/30/2025 | SGSOV Not Ready | KENNETH ROBERTS |
| Smoke Detectors | 6/30/2025 | Not Ready for Inspection | KENNETH ROBERTS |
| Final | 8/8/2025 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Final | 8/8/2025 | Not Ready for Inspection | BRIAN KELLY |
| Green Building Rough | 8/8/2025 | Not Ready for Inspection | BRIAN KELLY |
| Reinforced Masonry Frame | 8/8/2025 | Not Ready for Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 8/8/2025 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 8/8/2025 | Not Ready for Inspection | BRIAN KELLY |
| Final | 11/10/2025 | Partial Approval | KENNETH ROBERTS |
| Green Building Final | 11/10/2025 | Approved | KENNETH ROBERTS |
| Green Building Rough | 11/10/2025 | Approved | KENNETH ROBERTS |
| Reinforced Masonry Frame | 11/10/2025 | Approved | KENNETH ROBERTS |
| SGSOV-Seismic Gas S/O Valve | 11/10/2025 | SGSOV No Gas | KENNETH ROBERTS |
| Smoke Detectors | 11/10/2025 | Approved | KENNETH ROBERTS |