13241 W CUMPSTON ST 91401

Certificate Information: 13241 W CUMPSTON ST 91401

Application / Permit
23016-10000-39915
Plan Check / Job No.
B23LA21525
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. 1. CONVERT (E) 329 SQ FT 2-CAR GARAGE INTO A.D.U PER STATE LAW
Permit Issued
Issued on 5/1/2024
Issuing Office
Current Status
CofO Issued on 4/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/14/2023 APPLICANT
Assigned to Plan Check Engineer 11/16/2023 KHUONG TRUONG
Corrections Issued 11/17/2023 KHUONG TRUONG
Plan Check Approved 4/27/2024 KHUONG TRUONG
Issued 5/1/2024 APPLICANT
CofO in Progress 2/10/2025 RYAN SALAZAR
Permit Finaled 4/8/2025 RUBEN SALAS
Permit Finaled 4/8/2025 RUBEN SALAS
CofO Issued 4/8/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/10/2024 BIAINA HARITUNIAN
Sewer availability Cleared 4/10/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 4/17/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 4/24/2024 RIDWAN HARDY
Construction within easement Cleared 4/24/2024 RIDWAN HARDY

Contact Information

Contractor Eco Renovate Pros; Lic. No.: 1054754-B       ,
Contractor Riga Builders Inc; Lic. No.: 1054754-B       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/6/2024 Partial Approval RYAN SALAZAR
Sewer 9/6/2024 Approved RYAN SALAZAR
Excavation/Setback/Form/Re-Bar 9/17/2024 Approved RYAN SALAZAR
PLUMBING-Rough 10/23/2024 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 11/13/2024 Approved RYAN SALAZAR
Green Building Rough 11/13/2024 Approved RYAN SALAZAR
PLUMBING-Rough 11/13/2024 Approved RYAN SALAZAR
Drywall Nailing 11/20/2024 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 11/20/2024 Approved MICHAEL CORTEZ
Shower Pan 11/20/2024 Approved MICHAEL CORTEZ
ELECTRICAL-Rough 1/31/2025 Approved RYAN SALAZAR
Final 1/31/2025 Corrections Issued RYAN SALAZAR
Green Building Final 1/31/2025 Not Ready for Inspection RYAN SALAZAR
HVAC-Rough 1/31/2025 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 1/31/2025 SGSOV Approved RYAN SALAZAR
Smoke Detectors 1/31/2025 Approved RYAN SALAZAR
Final 2/7/2025 OK to Issue CofO RYAN SALAZAR
Green Building Final 2/7/2025 Approved RYAN SALAZAR