13241 W CUMPSTON ST 91401
Certificate Information: 13241 W CUMPSTON ST 91401
- Application / Permit
- 23016-10000-39915
- Plan Check / Job No.
- B23LA21525
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. 1. CONVERT (E) 329 SQ FT 2-CAR GARAGE INTO A.D.U PER STATE LAW
- Permit Issued
- Issued on 5/1/2024
- Issuing Office
- Current Status
- CofO Issued on 4/8/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/14/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 11/16/2023 | KHUONG TRUONG |
| Corrections Issued | 11/17/2023 | KHUONG TRUONG |
| Plan Check Approved | 4/27/2024 | KHUONG TRUONG |
| Issued | 5/1/2024 | APPLICANT |
| CofO in Progress | 2/10/2025 | RYAN SALAZAR |
| Permit Finaled | 4/8/2025 | RUBEN SALAS |
| Permit Finaled | 4/8/2025 | RUBEN SALAS |
| CofO Issued | 4/8/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/10/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 4/10/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/17/2024 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 4/24/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 4/24/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Eco Renovate Pros; Lic. No.: 1054754-B | , |
| Contractor | Riga Builders Inc; Lic. No.: 1054754-B | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/6/2024 | Partial Approval | RYAN SALAZAR |
| Sewer | 9/6/2024 | Approved | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 9/17/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 10/23/2024 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 11/13/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 11/13/2024 | Approved | RYAN SALAZAR |
| PLUMBING-Rough | 11/13/2024 | Approved | RYAN SALAZAR |
| Drywall Nailing | 11/20/2024 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 11/20/2024 | Approved | MICHAEL CORTEZ |
| Shower Pan | 11/20/2024 | Approved | MICHAEL CORTEZ |
| ELECTRICAL-Rough | 1/31/2025 | Approved | RYAN SALAZAR |
| Final | 1/31/2025 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 1/31/2025 | Not Ready for Inspection | RYAN SALAZAR |
| HVAC-Rough | 1/31/2025 | Approved | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 1/31/2025 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 1/31/2025 | Approved | RYAN SALAZAR |
| Final | 2/7/2025 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 2/7/2025 | Approved | RYAN SALAZAR |