148 E 88TH PL 90003

Certificate Information: 148 E 88TH PL 90003

Application / Permit
23016-10000-39730
Plan Check / Job No.
B23LA21395
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**ePlan** EPLAN CONVERT (E) DETACHED GARAGE TO ADU PER CA Govt. Code 65852.2(e)(1)(A). All work per WFPP
Permit Issued
Issued on 6/17/2024
Issuing Office
Current Status
CofO Issued on 12/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/4/2023 APPLICANT
Assigned to Plan Check Engineer 12/7/2023 ALFREDO JARA
Corrections Issued 12/8/2023 ALFREDO JARA
Plan Check Approved 5/17/2024 EDWIN ESPIN
Issued 6/17/2024 APPLICANT
No Progress 12/13/2025 DEROLD HAUFF
CofO in Progress 12/13/2025 DEROLD HAUFF
CofO in Progress 12/29/2025 JOHN QUINTANILLA
Permit Finaled 12/30/2025 DEROLD HAUFF
CofO Issued 12/30/2025 DEROLD HAUFF
Permit Finaled 12/30/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/11/2024 ARNULFO CHAMU
Eng Process Fee Ord 176,300 Cleared 1/11/2024 ARNULFO CHAMU
Roof/Waste drainage to street Cleared 1/11/2024 ARNULFO CHAMU
Sewer availability Cleared 1/11/2024 ARNULFO CHAMU
ZI Cleared 1/16/2024 MAXFIELD VERMY
Tenant Habitability Plan Cleared 1/18/2024 ISMAEL HERNANDEZ
Construction near power lines Cleared 5/4/2024 RIDWAN HARDY
Construction within easement Cleared 5/4/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/24/2024 Approved MICHAEL LEWIS
Pre-Inspection 7/11/2024 Approved MICHAEL LEWIS
Footing/Foundation/Slab 8/26/2024 Approved MICHAEL LEWIS
Underground Mechanical 8/26/2024 Approved MICHAEL LEWIS
Pre-Inspection 9/26/2024 Approved MICHAEL LEWIS
PLUMBING-Rough 10/4/2024 Corrections Issued CRAIG DAVIS
PLUMBING-Rough 10/9/2024 No Access for Inspection JOHN QUINTANILLA
Underground Mechanical 10/16/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 2/14/2025 Approved ANTHONY RAMOS
ELECTRICAL-Rough 3/11/2025 Not Ready for Inspection JOHN QUINTANILLA
HVAC-Rough 3/11/2025 Not Ready for Inspection JOHN QUINTANILLA
Rough-Elec/Plmb/HVAC 3/11/2025 Corrections Issued JOHN QUINTANILLA
ELECTRICAL-Rough 3/19/2025 Approved JOHN QUINTANILLA
HVAC-Rough 3/19/2025 Approved JOHN QUINTANILLA
PLUMBING-Rough 3/19/2025 Approved JOHN QUINTANILLA
Wood Frame 3/19/2025 Approved JOHN QUINTANILLA
Insulation 4/9/2025 Approved ANTHONY RAMOS
Shower Pan 4/9/2025 Approved ANTHONY RAMOS
Drywall Nailing 4/17/2025 Corrections Issued ANTHONY RAMOS
Drywall Nailing 4/21/2025 Approved ANTHONY RAMOS
Service/Power Release 10/7/2025 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Final 10/16/2025 Corrections Issued JOHN QUINTANILLA
PLUMBING-Final 10/16/2025 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 11/17/2025 Approved JOHN QUINTANILLA
Final 11/17/2025 Corrections Issued JOHN QUINTANILLA
Green Building Final 11/17/2025 Not Ready for Inspection JOHN QUINTANILLA
Green Building Rough 11/17/2025 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 11/17/2025 SGSOV Approved JOHN QUINTANILLA
Smoke Detectors 11/17/2025 Approved JOHN QUINTANILLA
Final 11/21/2025 Not Ready for Inspection JOHN QUINTANILLA
Green Building Final 11/21/2025 Not Ready for Inspection JOHN QUINTANILLA
Final 11/26/2025 OK to Issue CofO JOHN QUINTANILLA
Green Building Final 11/26/2025 Approved JOHN QUINTANILLA