3674 S NORTON AVE 90018

Certificate Information: 3674 S NORTON AVE 90018

Application / Permit
23016-10000-39622
Plan Check / Job No.
B23LA21351
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL TO EXISTING SINGLE FAMILY DWELLING AND REPLACE FLAT ROOF TO GABLE ROOF AT REAR.
Permit Issued
Issued on 12/11/2023
Issuing Office
Metro
Current Status
Permit Finaled on 10/9/2024

Permit Application Status History

Submitted 11/9/2023 APPLICANT
Assigned to Plan Check Engineer 11/9/2023 SAMUEL GONZALEZ
Corrections Issued 11/9/2023 SAMUEL GONZALEZ
Plan Check Approved 12/8/2023 FERNANDO FLORES
Issued 12/11/2023 APPLICANT
Permit Finaled 10/8/2024 ANTHONY EGSON

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 11/13/2023 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 11/14/2023 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,
Engineer Nuno,, Arnulfo; Lic. No.: C88425 7057 DWIGHT WAY      SAN BERNARDINO, CA 92404

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/13/2023 Partial Approval ANTHONY EGSON
Footing/Foundation/Slab 1/4/2024 Corrections Issued ANTHONY EGSON
Deputy Drilled-In Anchors 1/11/2024 Conditional Approval DAVID FEILER
Deputy Wood Construction 1/11/2024 Conditional Approval DAVID FEILER
Footing/Foundation/Slab 1/12/2024 No Access for Inspection ENRIQUE MIRELES
Footing/Foundation/Slab 1/18/2024 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 1/29/2024 Partial Approval ANTHONY EGSON
BUILDING-Rough-Frame 2/13/2024 Approved ENRIQUE MIRELES
PLUMBING-Rough 2/13/2024 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 3/27/2024 Corrections Issued ANTHONY EGSON
HVAC-Rough 3/27/2024 Corrections Issued ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 4/4/2024 Partial Approval ANTHONY EGSON
ELECTRICAL-Rough 4/5/2024 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 4/9/2024 Corrections Issued BRENDAN MORELLI
HVAC-Rough 4/10/2024 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 4/11/2024 Approved ANTHONY EGSON
Pre-Inspection 4/11/2024 Partial Approval ANTHONY EGSON
PLUMBING-Rough 4/12/2024 Corrections Issued ANTHONY EGSON
HVAC-Rough 4/15/2024 Approved ANTHONY EGSON
PLUMBING-Rough 4/15/2024 Approved ANTHONY EGSON
BUILDING-Rough-Frame 5/15/2024 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 5/17/2024 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 5/20/2024 No Access for Inspection ANTHONY EGSON
Interior/Exterior Lathing 5/22/2024 Approved ANTHONY EGSON
BUILDING-Rough-Frame 5/24/2024 Approved ANTHONY EGSON
Insulation 5/29/2024 Approved JOSH MEISTER
BUILDING-Rough-Frame 5/31/2024 Approved ANTHONY EGSON
Drywall Nailing 6/4/2024 Not Ready for Inspection ANTHONY EGSON
Drywall Nailing 6/6/2024 Approved ANTHONY EGSON
Pre-Inspection 6/6/2024 Partial Inspection ANTHONY EGSON
Interior/Exterior Lathing 6/21/2024 Approved ANTHONY EGSON
Shower Pan 6/21/2024 Approved ANTHONY EGSON
Pre-Inspection 7/3/2024 Partial Approval ANTHONY EGSON
ELECTRICAL-Final 9/20/2024 Corrections Issued ANTHONY EGSON
Final 9/20/2024 Not Ready for Inspection ANTHONY EGSON
HVAC-Final 9/20/2024 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Final 9/20/2024 Corrections Issued ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 9/20/2024 SGSOV Not Ready ANTHONY EGSON
Smoke Detectors 9/20/2024 Approved ANTHONY EGSON
ELECTRICAL-Final 10/8/2024 Approved ANTHONY EGSON
Final 10/8/2024 Permit Finaled ANTHONY EGSON
HVAC-Final 10/8/2024 Approved ANTHONY EGSON
PLUMBING-Final 10/8/2024 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 10/8/2024 SGSOV Approved ANTHONY EGSON