298 S KENTER AVE 90049

Certificate Information: 298 S KENTER AVE 90049

Application / Permit
23016-10000-39603
Plan Check / Job No.
B23LA21328
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 12/21/2023
Issuing Office
Current Status
CofO Issued on 4/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2023 APPLICANT
Assigned to Plan Check Engineer 11/14/2023 ALEC MOUSAKHANIAN
Corrections Issued 11/15/2023 ALEC MOUSAKHANIAN
Applicant returned to address corrections 12/18/2023 ALEC MOUSAKHANIAN
Plan Check Approved 12/20/2023 ALEC MOUSAKHANIAN
Issued 12/21/2023 APPLICANT
CofO in Progress 4/16/2025 HERBERT GIRON
Permit Finaled 4/24/2025 RICHARD STEINBACH
CofO Issued 4/24/2025 RICHARD STEINBACH
Permit Finaled 4/24/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 11/29/2023 ANDREA SAINT-ANTONIN
Roof/Waste drainage to street Cleared 11/29/2023 ANDREA SAINT-ANTONIN
Sewer availability Cleared 11/29/2023 ANDREA SAINT-ANTONIN
Eng Process Fee Ord 176,300 Cleared 11/30/2023 ANDREA SAINT-ANTONIN
Grading Pre-Inspection Cleared 12/14/2023 SERGIO VALENZUELA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/19/2024 Approved ARAM AVEDISIAN
PLUMBING-Rough 3/19/2024 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 7/22/2024 Corrections Issued ARAM AVEDISIAN
HVAC-Rough 7/22/2024 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 7/22/2024 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 7/25/2024 Partial Approval ARAM AVEDISIAN
ELECTRICAL-Rough 7/25/2024 Approved ARAM AVEDISIAN
HVAC-Rough 7/25/2024 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/30/2024 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 8/1/2024 Approved ARAM AVEDISIAN
Green Building Rough 8/1/2024 Not Ready for Inspection ARAM AVEDISIAN
Insulation 8/1/2024 Approved ARAM AVEDISIAN
Drywall Nailing 8/21/2024 Approved KEVIN SARGSYAN
Interior/Exterior Lathing 8/21/2024 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Final 1/30/2025 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Final 2/28/2025 Approved JESUS RODRIGUEZ
Final 2/28/2025 Corrections Issued JESUS RODRIGUEZ
HVAC-Final 2/28/2025 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 2/28/2025 Corrections Issued JESUS RODRIGUEZ
Smoke Detectors 2/28/2025 Approved JESUS RODRIGUEZ
Final 3/12/2025 Corrections Issued HERBERT GIRON
HVAC-Final 3/12/2025 Approved HERBERT GIRON
PLUMBING-Final 3/12/2025 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 3/12/2025 SGSOV Not Ready HERBERT GIRON
BUILDING-Rough-Frame 4/16/2025 Approved HERBERT GIRON
Final 4/16/2025 OK to Issue CofO HERBERT GIRON
Green Building Final 4/16/2025 Approved HERBERT GIRON
Green Building Rough 4/16/2025 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 4/16/2025 SGSOV Approved HERBERT GIRON
Service/Power Release 4/16/2025 Approved HERBERT GIRON