2426 N NORTH BROADWAY 90031

Certificate Information: 2426 N NORTH BROADWAY 90031

Application / Permit
23016-10000-39587
Plan Check / Job No.
B23LA21319
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
EPLAN The scope of work is to structurally (seismically) upgrade the existing URM building. The retrofit is to comply with Appendix A, Chapter A1 of the 2022 California Existing Building Code with 2023 Los Angeles Amendments. The retrofit includes wall anchorage, parapet bracing, new plywood shear walls, and a new steel moment frame. This retrofit will be immediately followed by a full architectural tenant improvement (permitted separately) which will cover all non-structural code requirements.
Permit Issued
Issued on 1/18/2024
Issuing Office
Current Status
Permit Finaled on 10/29/2024

Permit Application Status History

Submitted 11/9/2023 APPLICANT
Assigned to Plan Check Engineer 11/16/2023 QUAN NGHIEM
Assigned to Zoning Architect 12/1/2023 QUAN NGHIEM
Corrections Issued 12/1/2023 QUAN NGHIEM
Quality Review Completed 12/4/2023 PETER KIM
Applicant returned to address corrections 12/14/2023 QUAN NGHIEM
Applicant returned to address corrections 12/15/2023 QUAN NGHIEM
Applicant returned to address corrections 12/22/2023 QUAN NGHIEM
Plan Check Approved 1/17/2024 QUAN NGHIEM
Issued 1/18/2024 APPLICANT
Permit Finaled 10/28/2024 RONALD JIMENEZ

Permit Application Clearance Information

Green Code Cleared 11/22/2023 MICHAEL AYERS
Zoning Plan Check Cleared 12/2/2023 Rosendo Medina
DAS Clearance Cleared 12/22/2023 Rosendo Medina

Contact Information

Contractor Vault Construction Inc; Lic. No.: 755571-B PO BOX 6239      LA QUINTA, CA 92248
Engineer Mcdonald,, James Alan; Lic. No.: NA4766       ,

Inspector Information

SEAN POMISH, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI
RAFAEL CORTES, (213) 202-2643 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/18/2024 Partial Inspection RONALD JIMENEZ
Light Gage Steel Frame 3/18/2024 Approved RONALD JIMENEZ
Floor/Roof Diaphrgm/Shear Wall 4/2/2024 Partial Approval RONALD JIMENEZ
Footing/Foundation/Slab 4/2/2024 Partial Approval RONALD JIMENEZ
Interior/Exterior Lathing 4/8/2024 Partial Approval RONALD JIMENEZ
Excavation/Setback/Form/Re-Bar 6/4/2024 Conditional Approval RONALD JIMENEZ
Floor/Roof Diaphrgm/Shear Wall 6/4/2024 Not Ready for Inspection RONALD JIMENEZ
Footing/Foundation/Slab 6/4/2024 Conditional Approval RONALD JIMENEZ
Wood Frame 6/4/2024 Conditional Approval RONALD JIMENEZ
Footing/Foundation/Slab 6/13/2024 Conditional Approval RONALD JIMENEZ
Wall Anchors 6/13/2024 Partial Approval RONALD JIMENEZ
Wood Frame 6/13/2024 Partial Approval RONALD JIMENEZ
Floor/Roof Diaphrgm/Shear Wall 8/5/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Drilled-In Anchors 8/8/2024 Conditional Approval RAMAZANALI ALMASI
Deputy Wood Construction 8/8/2024 Conditional Approval RAMAZANALI ALMASI
Floor/Roof Diaphrgm/Shear Wall 8/15/2024 Partial Inspection RONALD JIMENEZ
Final 10/28/2024 Permit Finaled RONALD JIMENEZ
Green Building Final 10/28/2024 Approved RONALD JIMENEZ
SGSOV-Seismic Gas S/O Valve 10/28/2024 SGSOV Approved RONALD JIMENEZ
Smoke Detectors 10/28/2024 Approved RONALD JIMENEZ